Capricorn Metals Ltd (ASX: CMM), Part 1 of 3
Updated: Oct 22

Abstract
Capricorn Metals Ltd (ASX: CMM) owns two gold projects in Western Australia. The Karlawinda Gold Project in the Pilbara has produced gold since June 2021 and produced 123,589 ounces in the year to 30 June 2026.[R1] The Mt Gibson Gold Project is in the Yalgoo Mineral Field and has not produced gold since 1998. In the Samso Gold Regions Series the company carries the label Producer elsewhere. Mt Gibson is near-term, because it produces gold at Karlawinda and has a published study and a stated start date for Mt Gibson.
The study is an updated Pre-Feasibility Study released on 27 July 2026. A Pre-Feasibility Study is the stage of study before a final, or definitive, feasibility study. It plans open pit and underground mining and a new plant treating 5 million tonnes of ore a year. It forecasts 3.51 million ounces of gold over 19.25 years, a cost to build of A$474 million with no contingency, the allowance for cost overruns, and an all-in sustaining cost of A$1,870 an ounce.[R2] The all-in sustaining cost is what it costs to produce each ounce and keep the mine running. The plan rests on an Ore Reserve of 3.67 million ounces at 1.0 gram of gold per tonne, written g/t. An Ore Reserve is the part of the gold in the ground that a study shows can be mined at a profit.
Capricorn has built this kind of mine before. Karlawinda is a large, low-grade open pit, and it was the lowest cost gold-only mine in Australia and New Zealand in the June quarter of 2026 on one industry survey.[R3] The company held A$535.0 million in cash and gold at 30 September 2026 and has no bank debt.[R4] It says it can fund Mt Gibson from that cash and from Karlawinda. Detailed plant design is finished and the main contracts are signed, subject to permits.
The mine cannot start until Western Australia approves it. The federal approval came on 30 June 2026. The State's public review closed on 27 September 2026. The State environmental decision and the secondary approvals, which are the plant licence, the water licences and the mining proposal, are still to come. Capricorn gives no date for them.[R4] The study is at pre-feasibility level and the board has not announced a final decision to build. The headline of 260,000 ounces a year applies to four of the nineteen years. On Samso's arithmetic the study's cash flow implies a cost of about A$1,910 an ounce, about A$40 above the stated all-in sustaining cost.
Capricorn bought Warriedar Resources in November 2025 for shares and options valued at about A$335 million. With it came the Golden Range Project, 65 to 100 kilometres north of Mt Gibson, with 1.38 million ounces of gold in a Mineral Resource.[R5][R6] A Mineral Resource is gold estimated to be in the ground. Golden Range is not in the Mt Gibson study and is not in Capricorn's group resource. It is the subject of a separate study due in the December quarter of 2026. More than half of its gold is in the lowest confidence category, and the largest deposit holds gold in sulphide minerals, which needs a different process from Mt Gibson's.
Samso places Capricorn Metals at WATCH & DYOR. The company has a producing mine, a large reserve and the money. The events that decide the timetable are the State approvals and the board's decision to build. The shares closed at A$14.54 on 8 October 2026, which values the company at about A$6.6 billion.[R7] A technical review of the share chart reads it as a long uptrend with a fall inside it since late August 2026.
All prices in this piece are as at the close of ASX trading on 8 October 2026. Global prices for gold are taken at the same time.
Contents
Snapshot
Prices below are as at the market data date in the line at the top of this workup. The share price and market capitalisation will have moved since then, up or down. Check a live quote before relying on any figure here.
Metric | Value |
Share price | A$14.54 (ASX close, 8 October 2026) |
Shares on issue | 457,143,296 |
Market capitalisation | A$6,646.9 million. Samso arithmetic, shares multiplied by the closing price |
52-week range of closing prices | A$9.41 to A$17.78 (Yahoo Finance daily closes) |
Cash and gold on hand | A$535.0 million at 30 September 2026, preliminary. No bank debt |
Producing mine | Karlawinda Gold Project, Pilbara, Western Australia. 123,589 ounces in the year to 30 June 2026 at an all-in sustaining cost of A$1,629 an ounce |
Karlawinda guidance, year to 30 June 2027 | 137,000 to 147,000 ounces at an all-in sustaining cost of A$1,900 to A$2,100 an ounce |
Development project | Mt Gibson Gold Project, Yalgoo Mineral Field, Western Australia. 100 per cent owned |
Mt Gibson Mineral Resource | 188.9 million tonnes at 0.9 g/t gold for 5.67 million ounces (31 March 2026). 83 per cent of the ounces are Indicated, the middle confidence category |
Mt Gibson Ore Reserve | 119.3 million tonnes at 1.0 g/t gold for 3.67 million ounces, all Probable, the lower of the two reserve categories (31 March 2026) |
Study | Updated Pre-Feasibility Study, 27 July 2026. Open pit and underground. New 5.0 million tonne a year plant |
Planned production | 3.51 million ounces over 19.25 years. 182,500 ounces a year on average. 260,900 ounces a year in Years 3 to 6 |
Pre-production capital | A$474 million (A$345 million plant and infrastructure, A$129 million mining). No contingency included |
All-in sustaining cost in the study | A$1,870 an ounce over the life of the mine (A$1,873 in the study's results table) |
Stated timing | Construction to start in the December quarter of 2026 and operations in the March quarter of 2028, both subject to approvals |
Approvals | Federal approval received 30 June 2026. State environmental decision and secondary approvals not yet received |
Golden Range Mineral Resource | 1.38 million ounces of gold (Warriedar Resources estimate, May 2025). Not in the Mt Gibson study or the group resource |
Dividends for the year to 30 June 2026 | 10 cents a share, fully franked |
Samso Gold Regions Series label | Producer elsewhere. Mt Gibson is near-term |
Samso Call | WATCH & DYOR |
Substantial holders, from the Capricorn Metals Annual Report as at 31 July 2026, as printed. BlackRock Group 40,307,296 shares, 8.82 per cent. Van Eck Associates Corporation 28,141,441 shares, 6.16 per cent. State Street Corporation 27,848,861 shares, 6.11 per cent. Vanguard Group 22,316,498 shares, 5.18 per cent. Executive Chairman Mark Clark holds 17,530,749 shares.
Share price context. Capricorn Metals closed at A$13.78 on 8 October 2025 and at A$14.54 on 8 October 2026, a rise of about 6 per cent over twelve months. The lowest close in that time was A$9.41 on 23 March 2026 and the highest was A$17.78 on 26 August 2026. The shares closed at A$11.90 on the last trading day before the Mt Gibson study and at A$13.70 on the day it was released, 27 July 2026.[R8] |
1 Why Capricorn Metals Gets a Workup
Capricorn Metals Ltd (ASX: CMM) is a gold producer with one mine and a plan for a second. The mine is Karlawinda, in the Pilbara, which has produced gold since June 2021. The plan is for the Mt Gibson Gold Project, an old mining centre 280 kilometres north-east of Perth that last produced gold in 1998. Mt Gibson is the reason for this workup. The company also owns the Golden Range Project to the north of it, bought in 2025.[R5][R9]
This workup is page 7 of the Samso Gold Regions Series. The series sorts ASX gold companies by the mineral fields of Western Australia, the administrative areas the State uses to register mining tenements. Mt Gibson is in the Yalgoo Mineral Field. Karlawinda is outside the region the series covers. The series has an Insight on the Yalgoo Mineral Field, which had not been published at the date of this workup. Samso listed Capricorn among the gold producers in The Gold Question on 21 June 2026.[R10]
In the series Capricorn carries the label Producer elsewhere. Mt Gibson is near-term. Samso uses the word near-term only where a company has published a study and stated a start date. Capricorn released an updated Pre-Feasibility Study, the stage of study before a final one, on 27 July 2026. The study schedules construction to start in the December quarter of 2026 and operations in the March quarter of 2028, both subject to approvals.[R2]
The label describes a stage, and three things were still open at the date of this workup. The federal approval came on 30 June 2026. The State environmental decision and the secondary approvals are still to come, with no date given.[R11][R4] The board has not announced a final decision to build. The study is at pre-feasibility level, with a stated accuracy of plus or minus 25 per cent and no contingency.[R2] What that means is the label tells a reader how far the paperwork has come. It gives no assurance that the mine is built on those dates. The State approval and the board's decision to build are the two things to watch.
Capricorn says it can fund Mt Gibson from its cash and from Karlawinda. It held A$535.0 million in cash and gold at 30 September 2026 and has no bank debt.[R4][R5] Its Executive Chairman, Mark Clark, oversaw the building of Karlawinda and, before that, of three mines at the Duketon Gold Project of Regis Resources.[R5] For a shareholder that means two things. On the company's account, the build does not depend on a loan. The person leading it has built this kind of mine before.
The workup is in three parts. Part 1 covers the company, Karlawinda, where Mt Gibson is and its mining history. Part 2 takes the Mt Gibson study in order, from the geology to the Mineral Resource, the Ore Reserve, the mine plan, processing, costs, funding and approvals. Part 3 covers Golden Range, the drilling outside the mine plan, four peer companies, the share price with a technical review of the share chart, the gold price, the main risks and Samso's concluding comments. This workup is not a valuation and gives no price target.
2 The Company and Who Owns It
Capricorn Metals is a Perth company with about 457 million shares on issue, no bank debt and a market capitalisation of about A$6.6 billion at A$14.54 a share on 8 October 2026.[R7] The Executive Chairman, Mark Clark, holds about 17.5 million shares, or 3.8 per cent on Samso's arithmetic. In the year to 30 June 2026 the company earned a statutory profit after tax of A$282.2 million on revenue of A$711.4 million, and declared its first dividends.[R5] Put together, this is a company that is making money, owes the banks nothing and has a chairman who holds a large parcel of the shares.
A short history
The documents Samso read do not give a full company history. Mark Clark and Mark Okeby joined the board on 8 July 2019. Construction at Karlawinda began in December 2019 and the first gold was poured at the end of June 2021.[R5][R9] Capricorn bought Mt Gibson in July 2021.[R12] It bought Warriedar Resources, and with it the Golden Range Project, in November 2025.[R5] The subsidiary list still carries companies in Madagascar and Mauritius. The Annual Report lists them as exploration services, commercial property and investment holding, and does not give their history.[R5] What that means is the present leadership dates from 2019. In a little over six years it built Karlawinda, bought Mt Gibson and bought Golden Range. The documents do not let Samso say more about the overseas subsidiaries.
The board and executives
The board has five directors. Four are independent and one, Mark Clark, is an executive. Three of the five have served at Regis Resources. Table 1, after the list, gives their holdings.[R5]
Mark Clark, Executive Chairman. An accountant. He was Managing Director of Regis Resources from May 2009 to November 2016, then Executive Chairman, and left that board in October 2018. The Annual Report says he oversaw the development of the three Regis mines at Duketon.
Mark Okeby, Non-Executive Director. A lawyer and a past director of Regis Resources, Westgold Resources and Lynas Corporation.
Myles Ertzen, Non-Executive Director. A senior executive at Regis Resources from 2009 to December 2018. He chairs the Audit Committee.
Bernard De Araugo, Non-Executive Director. A metallurgist.
Jillian Irvin, Non-Executive Director. A geologist, and Principal Geologist at the consultancy Entech.

In plain terms, the chairman and the two other directors who have served at Regis Resources hold nearly all of the directors' shares. Those three have money in the company alongside shareholders.
The executives named as key management are Paul Criddle, Deputy Chief Executive Officer, Tony Hinkley, Chief Operating Officer, Shane Clark, Chief Development Officer, and William Nguyen, Chief Financial Officer and Company Secretary.[R5] Mark Clark's total pay for the year was A$2,885,889, of which 58.37 per cent was tied to performance. His long-term performance rights, which convert to shares only if targets are met, are tested on Capricorn's shareholder return against a peer group over the three years to 30 June 2028.[R5] What that means is more than half of the chairman's pay depends on results, and the long-term part depends on how Capricorn shares perform against other companies.
Shares on issue and substantial holders
The company had 456,787,789 ordinary shares on issue at 31 July 2026, held by 7,477 shareholders. The ASX data feed showed 457,143,296 on 8 October 2026.[R5][R7] It also had 1,703,048 unquoted performance rights and 688,400 unquoted options exercisable at A$5.275 until 11 April 2028. The options were issued to Warriedar option holders in the acquisition. The largest share issues of the past two years were 33,333,334 shares at A$6.00 in November 2024, which raised A$200 million for Mt Gibson and the Karlawinda expansion, 17,721,519 shares in March 2025 to close the hedge book, and 23,821,474 shares in November 2025 to buy Warriedar.[R5] For a shareholder that means the share count has grown through three large issues in two years, each for a stated purpose. The rights and options still on issue are small beside about 457 million shares.
Four fund managers are listed as substantial holders, which means each has declared 5 per cent or more. Table 2 gives them as the Annual Report prints them. The printed percentage for Vanguard Group is 5.18. On Samso's arithmetic 22,316,498 shares is 4.89 per cent of the 456,787,789 on issue. The total row prints 26.27 per cent, and 118,614,096 shares is 25.97 per cent on the same arithmetic.[R5]

In practical terms, this workup shows the holdings as printed. On either set of percentages, four large fund managers hold about a quarter of the company.
Results for the year to 30 June 2026
Revenue, profit and operating cash flow all rose on the year before. The average gold price received was A$6,241 an ounce against A$4,463. Table 3 gives the main lines. The company reports two profit figures. The statutory figure follows the accounting standards. The underlying figure adds back two non-cash items, a A$58.0 million reduction to revenue left over from hedge contracts closed in earlier years, and a A$4.7 million fall in the value of its gold put options.[R5][R1]

All that means is the company sold a little more gold at a much higher price, and the extra revenue showed up in profit and in cash. The gap between the two profit figures is the two non-cash items, and no cash left the company for either in the year.
The company had no borrowings at 30 June 2026. It carried lease liabilities of A$20.3 million, which are amounts owed under leases. A large tax payment falls due during the Mt Gibson build. Capricorn paid A$18.7 million of income tax during the year and owed A$102.8 million at year end, because past deductions had kept its instalments low.[R5] It expects a single payment of A$90 million to A$100 million for FY26, the financial year to 30 June 2026, to be made in FY27, the year after.[R1] What that means is the cash balance at 30 June 2026 had a tax bill of A$90 million to A$100 million still to come out of it. The payment falls in the same year the company plans to start building Mt Gibson.
Cash and gold on hand was A$507.0 million at 30 June 2026 and A$535.0 million at 30 September 2026, the later figure preliminary.[R13][R4] The Chairman's letter says A$500 million of cash and gold where the quarterly says A$507.0 million. One page of the Annual Report gives operating cash flow as A$468.4 million where the cash flow statement gives A$470.2 million.[R5] In practical terms, this workup uses A$507.0 million from the quarterly and A$470.2 million from the cash flow statement. The differences are small beside either figure.
The company spent A$95.0 million on exploration and feasibility studies at its two projects in the year, and A$133.4 million on the Karlawinda expansion and early works at Mt Gibson. Capital commitments at 30 June 2026 were A$34.8 million, all for Karlawinda. No capital commitment for Mt Gibson is disclosed at that date.[R5] Put together, the accounts showed no capital commitment for Mt Gibson at 30 June 2026. That agrees with a board that has not announced a decision to build.
The hedge book and the put options
Capricorn no longer has any obligation to deliver gold at a fixed price. Hedging is an agreement to sell future gold at a price set today. It protects a miner if the price falls and costs it if the price rises.[R5]
The last hedges were closed in 2025. In March 2025 the company closed forward contracts over 55,000 ounces and issued 17,721,519 shares valued at A$8.02 each, A$142.1 million in all, for that closure. The Annual Report text gives the cost as A$138.1 million and its table gives A$140.3 million. In June 2025 it closed a call option over 16,700 ounces with a strike price of A$2,260 an ounce. The text gives that cost as A$47.1 million in cash and the cash flow statement shows A$48.9 million. All figures are as published.[R5] In practical terms, Capricorn paid, mostly in shares, to get out of selling gold at old fixed prices. It now sells every ounce at the market price, so it takes the full benefit of a rise and, apart from the small put option cover described below, the full hurt of a fall.
A further non-cash amount of A$27.3 million sat in the hedge reserve at 30 June 2026 and will reduce reported revenue as the old delivery dates pass.[R5] What that means is reported revenue will be A$27.3 million lower than the cash received for gold over that time. It is a carry-over in the accounts and no cash is owed.
The company also holds gold put options. A put option is a right, with no obligation, to sell gold at a set price, so it works as insurance against a fall. Capricorn bought them in March and June 2025 for A$7.8 million. They were carried at A$265,000 at 30 June 2026. The Annual Report does not disclose the ounces covered, the strike price or the expiry date.[R5] For a shareholder that means there is some insurance against a fall in gold, and the documents do not let a reader measure how much. At a carrying value of A$265,000 against a cost of A$7.8 million, Samso reads the cover as small.
Dividends
Capricorn paid its first dividend in April 2026, an interim of 5 cents a share. The board declared a final dividend of 5 cents on 27 August 2026, a total of A$22.8 million, for payment on 9 October 2026. Dividends for the year were 10 cents a share, or A$45.7 million. Both were fully franked, which means they carry a credit for company tax already paid that Australian shareholders can use against their tax.[R1][R5] On Samso's arithmetic 10 cents is about 0.7 per cent of the A$14.54 share price. The A$535.0 million cash figure at 30 September 2026 is before the final dividend. In plain terms, the dividend is small beside the share price. The board chose to pay shareholders while it prepares to build. The cash balance will be A$22.8 million lower once the final dividend is paid.
Other holdings
Warriedar Resources owned the Big Springs Gold Project in Nevada. In July 2026 Capricorn agreed to sell it to Sentinel Metals, an ASX company, for up to A$26.0 million. The price is A$8.5 million in cash, A$5.0 million in Sentinel shares and A$12.5 million that depends on milestones the Annual Report does not describe.[R5] The cash was received in the September 2026 quarter.[R4] Capricorn's substantial holder notice, dated 26 August 2026, shows it holding 9.906 per cent of Sentinel.[R14] All that means is Capricorn chose to sell the Nevada project and has turned it into cash and a shareholding. Only the A$8.5 million is in the bank. The rest depends on Sentinel's share price and on milestones a reader cannot see.
3 Karlawinda Gold Project, the Producing Mine
Karlawinda is a large, low-grade open pit gold mine that produced 123,589 ounces in the year to 30 June 2026 at an all-in sustaining cost of A$1,629 an ounce. Both figures were inside the company's guidance. An expansion of the plant was completed on 23 September 2026. Capricorn expects Karlawinda's cash to fund Mt Gibson, and Mt Gibson is planned as the same kind of mine.[R5][R15]
Where it is and what kind of mine
The mine is in the Pilbara region of Western Australia, 65 kilometres by road south-east of Newman. The Nyiyaparli People hold native title, the legal recognition of traditional rights over land, and Capricorn has a land access agreement with them.[R9]
The main deposit is called Bibra. The gold sits in broad zones up to 50 metres wide that dip gently to the west, which suits a wide, shallow pit. Grade is the amount of gold in each tonne of rock, measured in grams per tonne and written g/t. The mill treated ore at 0.92 g/t in FY26. A mine at that grade depends on moving and treating large tonnages at a low cost per tonne.[R9][R5]
Capricorn built Karlawinda between December 2019 and June 2021. Its presentation gives the build as 18 months and under A$180 million.[R9][R16] The reserve announcement of July 2026 says 564,000 ounces had been produced since the start. The presentation of August 2026 gives five-year production as 592,000 ounces. Both are as published.[R9][R16] Figure 1 shows the site after the expansion.

Figure 1. Karlawinda from the air after the expansion. The new crushing circuit and its conveyors are in the foreground, beside a square water pond. The original plant, with its row of round leach tanks, is at centre right. The open pits and the grey and red waste dumps fill the background. Company photograph reproduced from a public ASX release, with attribution. Capricorn Metals, September 2026 Quarterly Production Update, 5 October 2026, page 2.[R4]
In practical terms, either figure tells a reader the same thing. Karlawinda has produced well over half a million ounces in five years, from a mine the company says it built in 18 months.
Production and costs in the year to 30 June 2026
Table 4 shows the four quarters. Production was steady at about 30,000 ounces a quarter and the all-in sustaining cost stayed between A$1,617 and A$1,648 an ounce. Guidance for the year was 115,000 to 125,000 ounces at A$1,530 to A$1,630 an ounce. The company says higher gold prices added about A$100 an ounce to royalties compared with what guidance assumed. A royalty is a payment to a government or another party based on the gold produced or sold.[R13][R5]

What that means is the mine ran evenly all year. Production landed near the top of guidance. Cost landed at the top of its range too, and the company puts that down to royalties rising with the gold price.
The strip ratio, the volume of waste moved for each unit of ore, was 7.72 against 5.27 in FY25. The company says the faster mining rate was needed for the expanded plant.[R5][R13] In plain terms, the mine moved far more waste for each tonne of ore than the year before. Moving waste costs money and produces no gold on the day, so a reader should watch whether the ratio stays this high.
Aurum Analytics, which compiles the costs that miners report each quarter, names Karlawinda as the lowest cost gold-only operation in Australia and New Zealand for the June quarter of 2026, at A$1,648 an ounce. The simple average for the mines in its survey was A$2,768 an ounce.[R3] For a shareholder that means Karlawinda produced gold for far less than the average mine in that survey. A mine at the low end of the cost table can keep earning at a gold price that hurts others.
The expansion and the guidance for the year to 30 June 2027
The Karlawinda Expansion Project added a second crushing, grinding and leaching circuit beside the first. Plant capacity rose from about 4 million tonnes a year to 6.5 million tonnes a year. Capricorn expects production of about 150,000 ounces a year.[R15][R5] The company says the work took 12 months and was finished on schedule and within budget.[R15][R4] The documents Samso read do not state the budget or the final cost. The Annual Report gives the date of board approval as October 2025 on two pages and cites an announcement of 29 October 2024 on another.[R5] Put together, the bigger plant is built, which takes one construction job off the list before Mt Gibson starts. A reader cannot check the statement on budget, because no budget or final cost is given.
Guidance for FY27 is 137,000 to 147,000 ounces at an all-in sustaining cost of A$1,900 to A$2,100 an ounce, with A$70 million to A$85 million of growth capital. The cost range is about A$270 to A$470 an ounce above the FY26 result. The company says part of the reason is that it raised the gold price used to design the pit from A$2,200 to A$2,600 an ounce, which brings lower grade ore into the plan and keeps the mine life above ten years.[R13] At the middle of the range, A$2,000, and a gold price of A$5,969 an ounce on 8 October 2026, the margin is about A$3,969 an ounce on Samso's arithmetic.[R17] What that means is Karlawinda is guided to produce more gold in FY27 and each ounce is guided to cost more. The margin is still wide at the present gold price. The first cost figures from the expanded plant are the thing to watch.
The September 2026 quarter
A preliminary update on 5 October 2026 gave production of 31,218 ounces from 1,133,000 tonnes milled at 0.94 g/t and 91.7 per cent recovery, which the company says is in line with its plan. Costs are due in the full quarterly report later in October 2026. Cash and gold on hand rose from A$507.0 million to A$535.0 million. The company gives the underlying cash build as A$62.2 million. That figure is before A$42.7 million of capital spending at the expansion and at Mt Gibson, and before the A$8.5 million received from the Big Springs sale.[R4] In plain terms, the company added A$62.2 million of cash in three months before spending on growth. After that spending, the cash and gold balance still rose.
Reserve, mine life and royalties
The Karlawinda Ore Reserve was 76.4 million tonnes at 0.6 g/t for 1.57 million ounces at 31 March 2026. All of it is in the Probable category, the lower of the two levels of confidence a reserve can carry. The Mineral Resource was 160.0 million tonnes at 0.6 g/t for 2.99 million ounces. Both are reported under the JORC Code, the Australasian standard for reporting resources and reserves.[R9]
The reserve rose after drilling below the old pit design, a lower cut-off grade of 0.3 g/t and the higher design gold price. The cut-off grade is the lowest grade treated as ore. The company states the mine life as 10 years, as more than 10 years and as approaching 11 years in documents issued within about two months of each other.[R9][R5][R15] It gives three figures for the size of the Karlawinda ground, 2,052 square kilometres, 3,425 square kilometres and 4,000 square kilometres. All are as published.[R9][R16][R5] In practical terms, a reader can take the mine life as about ten years and treat the size of the ground as unsettled. Part of the reserve growth comes from counting lower grade rock as ore, which the company gives as one reason for the higher cost guidance.
Two royalties apply. The State of Western Australia takes 2.5 per cent of revenue. South32 holds a 2 per cent net smelter royalty, a share of the revenue from metal sold after refining and transport costs. Royalties charged to cost of sales were A$42.9 million in FY26. BHP holds a right to buy back 70 per cent of the project, which applies only if resources reach 5 million ounces of gold or 120,000 tonnes of nickel.[R13][R5][R9] All that means is two parties are paid from each ounce before Capricorn, and the payments grow when the gold price rises. The BHP right matters only if the resource grows well beyond its present 2.99 million ounces.
Why Karlawinda matters to Mt Gibson
Mt Gibson is planned as the same kind of operation, a large open pit feeding a plant of 5 million tonnes a year, at a reserve grade of 1.0 g/t against 0.6 g/t at Karlawinda.[R2][R9] Capricorn says cash from Karlawinda gives it the capacity to fund Mt Gibson.[R5] The published calls on that cash are the Mt Gibson capital of A$474 million in the study, a tax payment of A$90 million to A$100 million, Karlawinda growth capital of A$70 million to A$85 million and dividends. Samso's concern is that Karlawinda's cost guidance at its midpoint is more than a fifth above the FY26 result, which narrows the margin that funds the build if the gold price falls. The section on funding, approvals and the timetable, in Part 2, sets out the arithmetic.
4 Where Mt Gibson Is and What Is Already There
Mt Gibson is an old mine site close to a sealed highway, with a new 400-room camp, an access road, an airstrip and water bores in place, and no processing plant. Capricorn bought it in July 2021 for A$39.6 million and two royalties, and has since bought ground to the north that takes its holding in the district to a stated 4,519 square kilometres.[R12][R16]
Location and access
The project is about 280 kilometres north-east of Perth and less than 10 kilometres from the Great Northern Highway, which a 10 kilometre access road joins to the site. It is 65 kilometres north-east of the town of Wubin.[R9][R13][R12] Figure 2 shows the project at the southern end of Capricorn's ground.

Figure 2. Capricorn's ground in the Mt Gibson region, outlined in solid blue, runs about 160 kilometres from the Mount Gibson Gold Project in the south to the Golden Range Project in the north. The dashed blue outline marks ground where the legend shows precious metals tenements. Yellow circles mark the Orion and Ricciardo deposits, which the legend calls flagship deposits. The pick and shovel symbols mark operating mines owned by others. The background colours are the State's interpreted bedrock geology. Grid numbers are metres, so the grid lines are 50 kilometres apart, and the scale bar is 20 kilometres. Company map reproduced from a public ASX release, with attribution. Capricorn Metals, Annual Report 2026, 27 August 2026, page 72.[R5]
The study says the project area is not subject to native title, following a Federal Court determination in May 2015. Capricorn has a heritage agreement with two Badimia corporations for the life of the project.[R2] What that means is the site is close to a sealed highway from Perth, which helps with moving people, fuel and equipment. On the study's account native title does not apply to the project area, and a heritage agreement is in place.
The 2021 purchase
Capricorn announced the purchase on 28 July 2021, through two agreements completed together. It bought Crimson Metals Pty Ltd from Avenger Projects Ltd. Crimson held priority applications for licences over most of the project area. It also bought mining tenure, mining information and infrastructure from Extension Hill Pty Ltd.[R12]
The price was A$39.6 million, paid as A$25.6 million in cash and 7.65 million Capricorn shares valued at A$14.0 million. Avenger also received a 1 per cent net smelter royalty on all minerals, which for gold applies to production above 90,000 ounces. A second royalty came with the ground, payable to St Barbara, at A$10 for each ounce of gold produced above 20,000 ounces from certain leases. The 2021 announcement lists 17 leases for it and the July 2026 study lists 15.[R12][R2] The section on capital and operating costs, in Part 2, covers the royalties in the study.
At the time of purchase Capricorn estimated a Mineral Resource of 79.7 million tonnes at 0.8 g/t for 2,083,000 ounces, all in the Inferred category, the lowest level of confidence. It put the purchase cost at less than A$20 for each resource ounce.[R12] The resource at 31 March 2026 was 5.67 million ounces.[R9] Put together, Capricorn paid A$39.6 million for ground that then held 2,083,000 ounces at the lowest level of confidence. Its drilling has since taken the resource to 5.67 million ounces. The two royalties stay with the ground and are paid out of future production.
How large the ground is
The area figures the company has published do not form one series, so Table 5 lists each with its source. The figure of 4,519 square kilometres appears in the announcement of 27 July 2026 on Range 500, the company's production aspiration, and in the August 2026 presentation, with no breakdown.[R6] One slide attaches it to Mt Gibson and another to the combined ground including Golden Range. Samso did not locate a current figure for the Mt Gibson ground alone.[R16][R5]

In practical terms, a reader should take 4,519 square kilometres as the company's figure for the whole district and should not add the rows together. How much of it belongs to Mt Gibson alone is not published.
Ground bought since 2025
Capricorn has made six purchases of ground around Mt Gibson and Golden Range since mid 2025. The largest was Warriedar Resources, bought for shares in November 2025, which the section on Golden Range, in Part 3, covers. Table 6 lists the five smaller ones. Each was paid mostly in Capricorn shares. The Yalgoo and Extension Hill agreements each carry two further payments of A$750,000, one if Capricorn announces a resource of more than 75,000 ounces of gold on the ground and one if its board decides to mine there.[R5][R18][R19][R20]

All of it is exploration ground. Capricorn plans mapping and sampling first, with work on the Yalgoo and Extension Hill ground designed to confirm targets for drilling in the first half of FY27.[R18][R19][R20] What that means is the company has been buying up the district in small parcels and paying mostly with shares, which saves cash. It is all early ground, and the work that would show whether it holds gold worth mining is still ahead.
What is on site now
The old mill was removed in 2009 to 2010, as the section on the mining history sets out. Figure 3 shows one of the old pits as it is today.

Figure 3. The Orion pit at Mt Gibson holds water and has not been mined since the 1990s. The benches cut by the old operators are visible in the pit walls, and a haul road with two light vehicles on it runs along the left-hand edge. Company photograph reproduced from a public ASX release, with attribution. Capricorn Metals, Annual Report 2026, 27 August 2026, page 12.[R5]
In 2021 Capricorn took over a 10 kilometre gravel access road, a gravel airstrip and hangar, a camp of about 60 rooms, four houses, offices, a workshop and sheds.[R12] It has since built a 400-room accommodation village, shown in Figure 4, and A$33.8 million was moved into the accounts as plant and equipment for it.[R5] The study gives two dates for its completion, the March 2025 quarter on one page and July 2025 on another.[R2]

Figure 4. The accommodation village at Mt Gibson is built. Rows of room blocks sit either side of a central kitchen and mess building, with a sports court between them. Capricorn gives the size as 400 rooms. Company photograph reproduced from a public ASX release, with attribution. Capricorn Metals, Mt Gibson PFS Update, 27 July 2026, page 2.[R2]
Capricorn has drilled 13 production bores. No power station is on site and no power contract had been announced in the documents Samso read. The section on processing and metallurgy, in Part 2, covers the water and power plans.[R2] For a shareholder that means the camp, the road, the airstrip and the water bores are in place before approval. On either date in the study, the camp is finished. The two large items still missing are the processing plant and the power supply.
Money spent to date
The company does not publish a single figure for what it has spent on Mt Gibson. The parts that are stated are the A$39.6 million purchase, the A$33.8 million moved into plant and equipment for the camp, A$1.2 million of development capital in the June 2026 quarter and A$2.1 million in the September 2026 quarter.[R5][R13][R4] Exploration spending is reported for the group only.[R5] In plain terms, a reader cannot tell from the documents what Mt Gibson has cost so far. The stated parts leave out the drilling and the studies, so the full figure is higher than those parts add up to.
The company has spent this money ahead of State approval. The section on funding, approvals and the timetable, in Part 2, covers that decision.
5 The Mining History of Mt Gibson
Mt Gibson produced about 868,000 ounces of gold between 1986 and 1998 from shallow pits, a small underground mine and a leach dump. Most of that gold came from weathered rock near the surface. A restart study begun in 2003 found the remainder uneconomic, and three companies drilled beneath the pits between 2003 and 2008 without locating significant high grade gold. Capricorn's plan goes deeper, into fresh rock.
This history comes from Capricorn's announcements and from the annual reports the old operators lodged with the State, held on the open file system known as WAMEX, together with a bulletin of the Geological Survey of Western Australia. Samso read the WAMEX reports on 5 October 2026 for the Gold Regions Series research. They were not re-opened for this workup, so every WAMEX figure below rests on the extracts in Samso's research files. The bulletin and the Legend Mining announcement of 2005 are cited from the same files.
Discovery and start in 1986
Prospectors worked small gold shows in the area long before the modern mine. Legend Mining's 2010 report dates the finds to between 1910 and 1916 and puts their production at less than 10 kilograms of gold.[R21] Capricorn's study dates the early production to the 1930s.[R2]
The modern mine began with gold found in laterite. Laterite is the hard, iron-rich gravel layer that forms at the surface after long weathering. Reynolds began exploring the area in 1980, and seven mining leases were granted in November 1984.[R22][R23] Reynolds formed a joint venture with Forsayth, which ran the operation. Capricorn's study says the joint venture began operations in 1986, mining 6.5 million tonnes of laterite ore.[R2] The joint venture's report for 1987 says the agreement was signed in 1987. The dates conflict as written.[R23]
The Geological Survey bulletin says laterite mining started in 1986 and that production from oxide and sulphide ore in the bedrock started in 1988. It records 2,446.5 kilograms of gold from 752,041 tonnes of ore at Mount Gibson to 31 December 1987. That is about 78,700 ounces on Samso's conversion.[R24] In practical terms, the exact start date does not change the picture. Modern mining began in the mid 1980s on gold found in the surface gravel, and moved into the rock beneath within about two years.
Owners in order
Table 7 lists who held the project and when. Capricorn's documents name Reynolds, Forsayth and Camelot Resources. The WAMEX reports add Pacmin, Oroya, Barrick, Legend Mining and Oz Minerals, the companies that held the ground after the mine closed.[R25][R26][R27][R21]

All that means is the ground has passed through many hands since the mine closed, and none of the owners between 1998 and 2021 brought it back into production. Barrick and Oz Minerals each looked at it and withdrew.
How much gold the mine produced
Two totals are on record and they differ by ten ounces. The old operators' reports give 868,478 ounces from 16,477,882 tonnes of ore at 1.64 g/t, including the leach dump.[R27][R21] Capricorn's 2021 announcement and page 8 of its 2026 study give 868,468 ounces. The technical appendix of the same study gives 868,478 ounces.[R12][R2] Table 8 sets out each version.

The end dates differ as well. Capricorn's 2021 announcement gives production between 1986 and 1999. The operators' reports give the end of mining as the end of 1997, the last milling as June 1998 and the end of leaching as November 1998. Barrick's 2005 report, lodged as an appendix to Oroya's, says mining continued until June 1997 and the leach was shut down by February 1999.[R27] In July 2021 Mark Clark described the last production as over 30 years ago. On the operators' dates it was about 23 years before.[R12] In practical terms, this workup uses about 868,000 ounces and treats the mine as having stopped in 1998. The differences are too small to change how a reader sees the old mine.
What kind of ore was mined
The old mine treated mostly weathered rock. Oxide is the soft, weathered rock nearest the surface. Transitional rock is partly weathered. Fresh rock, also called primary, is the hard unweathered rock below, where the gold usually sits with sulphide minerals, which are compounds of metal and sulphur such as pyrite. Oxide ore is cheaper to dig and to grind than fresh ore.
Oroya's 2005 report says about one third of the gold came from laterite, one third from oxide and one third from primary sulphide ore that was not refractory. Refractory ore is ore whose gold cannot be recovered by ordinary leaching. Barrick's report, an appendix to the same document, says about 77 per cent of production came from laterite and oxide material. The two statements do not agree.[R27] On either statement, most of the old gold came from laterite and oxide, the soft material near the surface.
In 1990 the joint venture produced 67,471 ounces and milled 857,455 tonnes at a head grade of 2.85 g/t.[R28] That grade is close to three times the 1.0 g/t in Capricorn's present reserve. Capricorn says the old plant recovered more than 90 per cent of the gold, which it reads as a sign the ore treated then was free-milling, meaning the gold leaches without extra treatment.[R12] What that means is the mill in 1990 treated rock nearly three times richer than the rock in the new plan. The new plan has to earn its money from large tonnages at a low cost per tonne, as Karlawinda does.
Legend Mining described the plant in 2005 as a carbon in leach plant on care and maintenance, meaning shut but looked after.[R29] Carbon in leach, written CIL, is the standard gold process in which ground ore is mixed with a cyanide solution that dissolves the gold and with carbon that collects it. Figure 5 shows the line of old pits with the outlines Capricorn drew around them in 2021.

Figure 5. The old Mt Gibson pits lie in one line about 8 kilometres long, running north-north-east. Red dots are historic pits and prospects. The yellow lines are the outlines of the pit shells Capricorn used for its 2021 resource estimate at a gold price of A$2,000 an ounce. The white line is the boundary of the project area at the time of purchase. Green lines mark the company's cross sections. The scale bar is 2 kilometres. Company map reproduced from a public ASX release, with attribution. Capricorn Metals, Acquisition of Mt Gibson Gold Project, 28 July 2021, page 5.[R12]
The dump leach and the Wombat underground mine
Low grade laterite was treated on a dump leach. Ore is stacked on a pad and sprinkled with cyanide solution, and the gold is collected from the liquid that drains out. The 4 million tonne dump produced 68,868 ounces and ran until November 1998.[R27] Capricorn calls the same facility a heap leach, and the old pad is now part of its Ore Reserve at 3.5 million tonnes at 0.4 g/t for 50,000 ounces.[R9] In plain terms, the old dump still holds enough gold for Capricorn to count 50,000 ounces of it in the reserve. That is a small part of the reserve.
The only underground mine was Wombat, a small high grade deposit of quartz and sulphide found in Camelot's time.[R2] In the year to 30 January 1998 it produced 13,995 ounces from 51,541 tonnes at 8.45 g/t.[R30] Legend's consultants wrote in 2010 that, apart from Wombat, grades beneath the pits had generally been too low to support underground mining.[R21] Capricorn's study plans an underground mine beneath the Orion South pit. For a shareholder that means the underground part of the new plan goes where the old record is thin. The only underground mine before it was small, and the old owners judged the rest too low in grade.
Closure and the attempts to restart
No report Samso read gives a full reason for the closure. Pacmin wrote that Camelot closed the mining operation in late 1997 after mining of the Wombat underground ore was complete, and that the remaining resources had not been mined due to economic constraints.[R25] Capricorn says the project went onto care and maintenance when the gold price was around A$450 an ounce.[R12] On these accounts, the mine closed with gold still in the ground that did not pay to mine at the price of the day.
Oroya studied a restart from 2003 and decided against it. Its study found the project unlikely to be economic at the gold price of the time. Samso's extract of the report records no figure for that price. The reasons listed were thin ore bodies in a system of many lodes, which meant high dilution, a high strip ratio, a high share of primary ore to oxide ore, which slowed the mill, and high costs for fuel, labour, earthmoving, steel and plant refurbishment.[R27][R21] Dilution is waste rock that gets mined with the ore and lowers its grade. A lode is a sheet-like body of mineralised rock. Samso reads this as a restart that failed on the rock and on costs as well as on the gold price. The new plan mines the same ground at a much higher gold price.
Three companies then drilled beneath the pits. Barrick drilled 13 diamond and six reverse circulation holes for 11,600 metres from 2003 to 2005. Diamond drilling cuts a solid core of rock and reverse circulation drilling returns rock chips. Legend's report says the Barrick drilling did not locate significant high grade gold under the pits. Legend drilled eight diamond holes and Oz Minerals five, and both reported weak or low grade zinc. Legend's consultants concluded in 2010 that a deposit of more than 500,000 ounces was considered unlikely.[R21] In plain terms, three companies looked under the pits for rich underground ore and the reports record no find that led to a mine. Capricorn's underground plan rests on drilling it has done since.
In 2009 to 2010 Legend dismantled and removed the gold mill, the plant equipment and the crushing circuit and removed the concrete footings.[R21] Capricorn's 2021 announcement describes the plant as decommissioned and removed.[R12] Any new operation needs a new plant.
Historical resources
The old operators published several estimates of what was left. All of them are historical and none was prepared under the JORC Code of 2012, so they cannot be compared with Capricorn's figures. Pacmin's 1999 table of resources remaining after closure totals 3,253,700 tonnes at 1.69 g/t for 178,102 ounces. Samso's extract records no cut-off, date, method or code with the table.[R25] Oroya's 2004 work gave reserves for five areas, also historical and not JORC 2012, and its report says the mining schedules did not produce an economically viable operation.[R27] All that means is these old numbers are background only. They show the old owners knew gold was left behind and could not make it pay. A reader should not set them beside Capricorn's resource.
What the history means for the new plan
The old operators mined laterite, oxide and near-surface ore from pits no deeper than about 100 metres and left the lower grade rock beneath.[R12][R25] Capricorn's plan is built on that deeper rock. Of its 5.67 million ounce Mineral Resource, the open pit fresh rock holds 3.83 million ounces and laterite and oxide together hold about 0.35 million.[R9] The plan mines it in large pits at about 1.0 g/t, at a study gold price of A$5,500 an ounce.[R2] Capricorn said in 2021 that less than 5 per cent of the 660,000 metres of old drilling went deeper than 150 metres.[R12]
The record shows a field that produced gold for 12 years through a plant that Capricorn says recovered more than 90 per cent. The factors Oroya listed, thin lodes, dilution and a high share of hard primary ore, describe the rock the new plan depends on. The old recovery figures came mostly from weathered ore, and the new plan treats mostly fresh ore. The sections on the Ore Reserve and on processing and metallurgy, in Part 2, set out how the study deals with each.
21 References and Sources
Every source used in this workup is listed below with its date. Each entry carries an identifier, and the same identifier appears in the body at the point that source is used, so any number, quotation or finding here can be traced back to the document behind it in one step.
[R1] Capricorn Metals Ltd, "Record FY Results and 5cps Fully Franked Final Dividend", ASX announcement, 27 August 2026. announcements.asx.com.au
[R2] Capricorn Metals Ltd, "Compelling Mt Gibson PFS Update", ASX announcement, 27 July 2026. The updated Pre-Feasibility Study for the Mt Gibson Gold Project, with JORC Table 1. announcements.asx.com.au
[R3] Aurum Analytics, "Australian & New Zealand Gold Operations, June Quarter 2026". aurumanalytics.com.au
[R4] Capricorn Metals Ltd, "September 2026 Quarterly Production Update", ASX announcement, 5 October 2026. Preliminary. announcements.asx.com.au
[R5] Capricorn Metals Ltd, "Annual Report to shareholders" for the year to 30 June 2026, ASX announcement, 27 August 2026. announcements.asx.com.au
[R6] Capricorn Metals Ltd, "Range 500 Aspiration", ASX announcement, 27 July 2026. announcements.asx.com.au
[R7] ASX company data feed for CMM, RXL, HRN, AAR and STN, header and key statistics, read on 9 October 2026. Shares on issue and closing prices of 8 October 2026. Market capitalisation is Samso arithmetic. asx.com.au
[R8] Yahoo Finance, daily closing prices for CMM.AX, to 8 October 2026, read on 9 October 2026. Highs, lows and percentage changes are Samso arithmetic on closing prices. finance.yahoo.com
[R9] Capricorn Metals Ltd, "Capricorn Gold Reserves Increase to 5.2 Million Ounces", ASX announcement, 27 July 2026. Ore Reserves and Mineral Resources at 31 March 2026. announcements.asx.com.au
[R10] Samso Insights, "The Gold Question", 21 June 2026. samso.com.au
[R11] Capricorn Metals Ltd, "Federal Environmental Approval Received for MGGP", ASX announcement, 30 June 2026. announcements.asx.com.au
[R12] Capricorn Metals Ltd, "Acquisition of Mt Gibson Gold Project", ASX announcement, 28 July 2021. announcements.asx.com.au
[R13] Capricorn Metals Ltd, "Quarterly Activities and Appendix 5B" for the June 2026 quarter, ASX announcement, 31 July 2026. announcements.asx.com.au
[R14] Capricorn Metals Ltd, Form 603 "Notice of initial substantial holder" in Sentinel Metals, 28 August 2026. announcements.asx.com.au
[R15] Capricorn Metals Ltd, "Karlawinda Expansion Project Completed on Schedule", ASX announcement, 23 September 2026. announcements.asx.com.au
[R16] Capricorn Metals Ltd, "Diggers and Dealers Mining Forum Presentation", ASX announcement, 4 August 2026. announcements.asx.com.au
[R17] Yahoo Finance, daily closing prices of COMEX gold futures (GC=F) and of the Australian dollar against the US dollar (AUDUSD=X), October 2023 to 8 October 2026, read on 9 October 2026. Australian dollar gold prices, percentage changes and day counts are Samso arithmetic on these series. finance.yahoo.com
[R18] Capricorn Metals Ltd, "Acquisition of Yalgoo Project", ASX announcement, 23 December 2025. announcements.asx.com.au
[R19] Capricorn Metals Ltd, "Acquisition of Extension Hill and Mungada Projects", ASX announcement, 19 February 2026. announcements.asx.com.au
[R20] Capricorn Metals Ltd, "Acquisition of Piastri Project", ASX announcement, 14 August 2026. announcements.asx.com.au
[R21] Legend Mining Ltd, Annual report, Combined Reporting Group C49/2002, 1 July 2009 to 30 June 2010, with two Predictive Discovery targeting reports as appendices, 2010. WAMEX open file report A88072, Department of Mines, Petroleum and Exploration, Western Australia. Historical. Read for the Samso Gold Regions Series research on 5 October 2026 and not re-opened for this workup.
[R22] Pacmin Mining Corporation (Oriole Resources), Annual report 1998/99, RAB and aircore drilling, 2000. WAMEX open file report A61298, Department of Mines, Petroleum and Exploration, Western Australia. Historical. Read for the Samso Gold Regions Series research on 5 October 2026 and not re-opened for this workup.
[R23] Reynolds Australia Mines Pty Ltd and Forsayth NL joint venture, Annual exploration report to December 1987, Mt Gibson Project, 1988. WAMEX open file report A22134, Department of Mines, Petroleum and Exploration, Western Australia. Historical. Read for the Samso Gold Regions Series research on 5 October 2026 and not re-opened for this workup.
[R24] Watkins, K.P. and Hickman, A.H., 1990. Geological evolution and mineralization of the Murchison Province, Western Australia. Geological Survey of Western Australia, Bulletin 137. Read for the Samso Gold Regions Series research and not re-opened for this workup. Geological Survey of Western Australia
[R25] Pacmin Mining Corporation (Oriole Resources), Annual report 1998 to 1999, 1999. WAMEX open file report A58134, Department of Mines, Petroleum and Exploration, Western Australia. Historical. Read for the Samso Gold Regions Series research on 5 October 2026 and not re-opened for this workup.
[R26] Mt Gibson Gold Pty Ltd, Combined annual report 1/2/2002 to 30/6/2002, 2002. WAMEX open file report A65153, Department of Mines, Petroleum and Exploration, Western Australia. Historical. Read for the Samso Gold Regions Series research on 5 October 2026 and not re-opened for this workup.
[R27] Oroya Mining Ltd, Annual report 2004 to 2005, with Barrick report TR 1149 as Appendix 1, 2005. WAMEX open file report A70866, Department of Mines, Petroleum and Exploration, Western Australia. Historical. Read for the Samso Gold Regions Series research on 5 October 2026 and not re-opened for this workup.
[R28] Reynolds Australia Metals Ltd, Mt Gibson Joint Venture, Annual report 1990, 1991. WAMEX open file report A32871, Department of Mines, Petroleum and Exploration, Western Australia. Historical. Read for the Samso Gold Regions Series research on 5 October 2026 and not re-opened for this workup.
[R29] Legend Mining Limited, "Legend to Acquire Mt Gibson Gold & Base Metal Project", ASX announcement, 2 August 2005. Read for the Samso Gold Regions Series research and not re-opened for this workup. legendmining.com.au
[R30] Camelot Resources NL, Combined annual report 31/01/97 to 30/01/98, Mt Gibson Gold Mine tenements, Volume 1, 1998. WAMEX open file report A53905, Department of Mines, Petroleum and Exploration, Western Australia. Historical. Read for the Samso Gold Regions Series research on 5 October 2026 and not re-opened for this workup.
22 Disclaimer
The information contained on this website is the writer's personal opinion and is provided to you for information only and is not intended to or nor will it create/induce the creation of any binding legal relations. There may be a conflict of interest present with commercial arrangements with companies and/or stock held. Samso or an associate may receive a commission for funds raised. The information or opinions provided herein do not constitute investment advice, an offer or solicitation to subscribe for, purchase or sell the investment product(s) mentioned herein. It does not take into consideration, nor have any regard to your specific investment objectives, financial situation, risk profile, tax position and particular, or unique needs and constraints. Accordingly, no warranty whatsoever is given, and no liability whatsoever is accepted for any loss arising, whether directly or indirectly as a result of this information. Investments are subject to investment risks, including possible loss of the principal amount invested. The value of the product and the income from them may fall as well as rise. You may wish to seek advice from an independent financial adviser before committing to purchase or invest in the investment product(s) mentioned herein. If you choose not to do so, you should consider whether the investment product(s) mentioned herein are suitable for you. The writer will not, in any event, be liable to you for any direct/indirect or any other damages of any kind arising from or in connection with your reliance on any information in and/or materials appended herein. The information and/or materials are provided "as is" without warranty of any kind, either express or implied. In particular, no warranty regarding accuracy or fitness for a purpose is given in connection with such information and materials.