Rox Resources Limited (ASX: RXL) is building a gold mine in Western Australia. It owns 100 per cent of the Youanmi Gold Mine, near Mt Magnet and about 480 kilometres north-east of Perth. Youanmi was mined in several periods between 1908 and 1997. Rox is reopening it as an underground mine and is building a new processing plant on the site. The company's target for first gold is the middle of 2027 (quarterly report, lodged 20 October 2026). It funds the work with money raised from shareholders and with bank loans. Some of the gold at Youanmi is refractory, which means it is locked inside other minerals and the standard treatment cannot recover it. The new plant is designed to treat that gold with a method called the Albion Process.

ASX code: RXL. Full legal name: Rox Resources Limited. Managing Director and Chief Executive: Phillip Wilding. Chairman: Stephen Dennis. The other directors are Nathan Stoitis, David Boyd and Alan Rule, all non-executive. Rox held A$59.3 million in cash at 30 September 2026 (quarterly report, lodged 20 October 2026).

Rox Resources projects

Rox has one project, the Youanmi Gold Mine in Western Australia.

A Mineral Resource is a company's estimate of the material in the ground that has reasonable prospects of being mined. It is stated as tonnes and grade and is reported under the JORC Code, the Australasian code for reporting mineral resources. The code has three confidence categories. Measured is the highest. Indicated means the drill holes are close enough together to give reasonable confidence in the tonnes and the grade. Inferred is the lowest, where the drill holes are further apart. An Ore Reserve is the part of the Measured and Indicated resource that a detailed study has shown can be mined at a profit. A reserve is either Proved or Probable, and Probable is the lower of the two.

  • Youanmi Gold Mine, near Mt Magnet and about 480 kilometres north-east of Perth. Gold. Rox owns 100 per cent of the 11 mining leases that hold the Youanmi mine. It also holds 90 per cent of the gold rights on two mining leases in the Currans joint venture (quarterly report, lodged 20 October 2026). The Mineral Resource is 12.4 million tonnes at 5.5 grams of gold per tonne, which contains 2,195,000 ounces of gold, as at 30 June 2026. Almost all of it, 2,105,000 ounces at 6.0 grams per tonne, is in the underground part. Of the total, 8.5 million tonnes at 5.9 grams per tonne for 1,606,000 ounces is Indicated. The other 3.9 million tonnes at 4.7 grams per tonne for 588,000 ounces is Inferred (ASX announcement, 9 September 2026).
  • Surrounding exploration ground. Rox holds exploration licences around the mine. It owns some outright. On the others it holds the rights to 90 or 100 per cent of the gold (quarterly report, lodged 20 October 2026).

The Ore Reserve is 4.8 million tonnes at 4.7 grams per tonne for 727,000 ounces, all of it Probable. The resource figure includes the reserve. The reserve cut-off, the lowest grade counted as ore, uses a gold price of A$3,200 an ounce (ASX announcement, 9 September 2026). The study's cost and revenue figures use A$5,200 an ounce (Definitive Feasibility Study, 13 November 2025).

Earlier owners produced about 667,000 ounces of gold at Youanmi before the mine closed in November 1997 (Definitive Feasibility Study, 13 November 2025).

The Youanmi study, funding and construction

Rox published a Definitive Feasibility Study for Youanmi on 13 November 2025. A definitive feasibility study is the most detailed of the three study levels a mining project goes through. The Youanmi study sets a production target of 5.7 million tonnes at 4.9 grams per tonne for 900,000 ounces of contained gold. The plant is assumed to recover 90.8 per cent of that gold, which gives 817,000 ounces produced. The study's results table states a mine life of 6.8 years. Its headline states an average of 117,000 ounces a year over a 7-year mine life.

When the study was published, the Ore Reserve covered about 75 per cent of the target ounces. The reserve then was 4.4 million tonnes at 4.8 grams per tonne for 674,000 ounces. A further 5 per cent was Indicated resource outside the reserve. About 20 per cent, or 178,000 ounces, was Inferred resource. The study cautions that Inferred resources carry a low level of geological confidence, and that there is no certainty the production target will be met. The reserve was updated to 727,000 ounces at 30 June 2026 (ASX announcement, 9 September 2026). The production target is still the one published in November 2025.

The study gives an all-in sustaining cost of A$1,978 an ounce, at an assumed gold price of A$5,200 an ounce. The all-in sustaining cost is an industry measure of what it costs to produce each ounce and keep a mine running. It leaves out the cost of building the mine. The study puts the capital cost before production at A$383 million, which includes a contingency of A$15 million on processing infrastructure. Capital spending after production starts is a further A$172 million over the mine life, and that amount is counted in the all-in sustaining cost. Capital and operating costs were estimated to an accuracy of plus or minus 10 to 15 per cent. The annual report says the A$383 million capital cost may be exceeded.

The plant is designed around the refractory gold, which the study puts at up to 25 per cent of the gold in Youanmi ore. That gold sits inside arsenopyrite, a mineral of iron, arsenic and sulphur. The plant will separate the sulphide minerals, which are minerals of metal and sulphur, from the rest of the ore. That step is called flotation and its product is called a concentrate. The concentrate then goes through the Albion Process. It is ground very finely and then partly oxidised with oxygen in tanks at normal pressure, which breaks down the arsenopyrite. Cyanide then dissolves the gold from the oxidised concentrate and from the rest of the ore.

The 90.8 per cent recovery is calculated from laboratory tests on two blended samples of drill core. The test work so far is at laboratory scale. The study lists the step from laboratory scale to plant scale as a risk, and says no pilot plant test work had been done. A pilot plant is a small trial version of the process. Glencore Technology is supplying the Albion Process under licence (annual report, lodged 17 September 2026).

Rox has raised A$218 million from shareholders, before costs, and arranged A$350 million of bank facilities for the build. The equity was a A$200 million placement and an A$18 million share purchase plan. The bank facilities are a A$300 million project loan, a A$20 million cost overrun facility and a A$30 million bank guarantee facility (annual report, lodged 17 September 2026).

The board approved a final investment decision in March 2026. The loan reached financial close on 2 October 2026. Rox drew A$90.2 million that day. After that drawdown A$229.8 million remained available under the project loan and the cost overrun facility (quarterly report, lodged 20 October 2026).

Rox has also bought gold put options over 40,400 ounces for the year to June 2028, at a price of A$5,700 an ounce. The company says that covers about half of forecast production for that year. The options cost A$9.7 million (annual report, lodged 17 September 2026).

Construction and mining are under way at Youanmi. The company said the processing plant was 39 per cent complete at 30 September 2026. Interquip is building it. The works approval, the last major approval, was granted in July 2026. The company describes Youanmi as fully permitted. The annual report says people within the company have developed mines before, and that the company itself has not.

Ore from underground development, the tunnelling that reaches the ore, is being stockpiled for the plant. The stockpile held 47,955 tonnes at 3.05 grams per tonne for 4,700 ounces of contained gold at 30 September 2026 (quarterly report, lodged 20 October 2026). The study plans a stockpile of about 190,000 tonnes at 3.3 grams per tonne before the plant starts (Definitive Feasibility Study, 13 November 2025). Rox blasted its first stope at the United North part of the mine, as reported on 9 November 2026. A stope is what we call the opening left where ore is blasted and removed, and stoping is the main production stage of an underground mine. The quarterly report named the oxygen supply contract as the last major contract outstanding. On 9 November 2026 it was still to be signed.

Rox is drilling below the current resource. The first results were reported on 5 November 2026. The first step-out hole, a hole drilled outside the known resource, intersected gold about 25 metres below the resource boundary. That result is not part of the Mineral Resource.

Rox will pay royalties on Youanmi gold. The Western Australian government royalty is 2.5 per cent. Venus Metals Corporation holds a 1 per cent net smelter royalty, which is a percentage of the money received from selling the gold, over the tenements held by Rox's subsidiary Oz Youanmi Gold, other than mining lease M57/10. The study's costs allow for those two, a total of 3.5 per cent (Definitive Feasibility Study, 13 November 2025). A native title mining agreement signed in August 2026 with the Badimia Barna claim group also includes a production-based royalty (quarterly report, lodged 20 October 2026).

Every Samso piece on Rox Resources

Newest first. Five published pieces as at 17 November 2026. Dates are in Perth time.

Samso Research

Samso Insights

Samso News

The Samso Research workup was published on 11 October 2026 and uses prices at 5 October 2026. Its headline resource, reserve and study figures match the ones on this page. Its cash figure is A$152.7 million at 30 June 2026. This page uses the 30 September 2026 figure. Since the workup the company has reported its September quarter, the first results from the deeper drilling and the first stope at United North. The 2018 piece was written before Rox's work at Youanmi.

Questions people ask about Rox Resources (ASX RXL)

What does Rox Resources do? It is building a gold mine. Rox owns the Youanmi Gold Mine, near Mt Magnet in Western Australia, which last operated in 1997. It is developing an underground mine there and building a new processing plant.

What is the Rox Resources share price? The ASX website shows the RXL share price. This page lists Samso's coverage and has no live price.

What is the latest announcement from Rox Resources? As at 17 November 2026 the company had lodged three announcements about the project in November. The first deep drilling results were released on 5 November. An update on stoping and construction followed on 9 November. A conference presentation was lodged on 10 November. The company's announcements page and the ASX list the newest ones.

Does Rox Resources produce gold? Rox's target for first gold is the middle of 2027. It is mining ore underground at Youanmi and stockpiling it while the processing plant is built.

Is Rox Resources worth looking at? This page gives no buy, sell or hold call, price target or valuation. Youanmi has a Mineral Resource, an Ore Reserve and a Definitive Feasibility Study. The company says it has its approvals, and its bank facilities reached financial close in October 2026. The plant is being built. The Samso Research workup goes through the company in detail.

This page is general information only.

Depth over hype.

Samso company research pages are independent research commentary for general information only. Nothing on this page is financial product advice, and it does not take into account any reader's objectives, financial situation or needs. Figures are drawn from public sources believed reliable at the stated dates but are not guaranteed, and market-sensitive numbers change daily. Samso or associated parties may hold positions in, or have commercial arrangements with, companies mentioned. Seek professional advice before making investment decisions. © Samso 2026, samso.com.au

Page last reviewed 17 November 2026.