Iron Bear Resources (ASX: IBR) - The Updated PFS Against Mines That Got Built
Iron Bear's updated study lifts the NPV to US$11.6 billion and the IRR to 17.9 per cent. Put on the same basis as Bloom Lake, Hope Downs, Simandou and other projects that were built, the return is in their range. The capital for each tonne of yearly capacity is above all of them.


Iron Bear Resources (ASX: IBR) released an updated pre-feasibility study for its Iron Bear magnetite project in Labrador, Canada, on 23 November 2026 [R1]. The post-tax net present value rose from US$9.0 billion to US$11.6 billion. The post-tax internal rate of return rose from 15.2 per cent to 17.9 per cent. Pre-production capital fell from US$4.25 billion to US$4.04 billion.
The comparison covers iron ore mines built since 2013, including Hope Downs in the Pilbara and Champion Iron's Bloom Lake restart, and large projects in other commodities. Bloom Lake's study is almost ten years old, so its dollar figures are brought forward to 2026 prices.
Iron Bear quotes its IRR in nominal terms, with inflation built into the model. Bloom Lake, Simandou and Quellaveco quote theirs in real terms, with inflation taken out. On a real basis Iron Bear's 17.9 per cent is about 15 per cent.
A note on the vocabulary and the sources Mining and processing terms are explained in plain English where they first appear, and all of them are collected again in "The vocabulary, in plain English" box at the back, just above the references. Each source carries an identifier, [R1] to [R35]. The same identifier appears in the text where the source is used, so any number can be traced to the document behind it. Where Samso has done the arithmetic, the text says so and shows the working. Where the company's documents give two different figures for the same thing, this article quotes both as they were published and names the document each came from. It does not attempt to resolve them. Disclosure. Noel Ong, who runs Samso, is a shareholder in Iron Bear Resources. |
Share prices are as at the close of ASX trading on 20 November 2026.
WHAT THIS PIECE COVERS 1.00 Iron Bear and the updated study Where the project is, what it plans to make and what the November update changed. 2.00 Where the extra US$2.6 billion of NPV came from The five changes the company made and what each added. Why Iron Bear's 17.9 per cent nominal is about 15 per cent in real terms. 4.00 Bloom Lake in today's dollars Champion Iron's 2017 restart study, brought forward to 2026 prices. 5.00 Hope Downs and the Pilbara builds What Rio Tinto and BHP spent. Neither published an IRR. 6.00 The magnetite and DR feed builds Iron Bridge, Kami and Simandou, the projects closest to Iron Bear. 7.00 Large projects in other commodities Jansen potash and Quellaveco copper. 8.00 The comparison side by side Published IRRs, a Samso model for Hope Downs 4, South Flank and Iron Bridge, and capital per tonne. 9.00 What the study leaves outside its numbers The power line, the tax holiday and the rail access. 10.00 The study against the share price Market value, cash and the money needed to reach a decision to mine. 11.00 The case against the comparison Why a pre-feasibility IRR and a built mine's IRR are different things. |
1.00 — IRON BEAR AND THE UPDATED STUDY
A 25.9 million tonne a year plan near Schefferville - Iron Bear Resources
The Iron Bear project is in Labrador, about 30 kilometres north-west of the town of Schefferville and close to the Quebec border [R1]. It is in the Labrador Trough, a belt of iron-bearing volcanic and sedimentary rock about 1,600 kilometres long that has been mined since 1954. FIG. 01 shows where it is against the comparison projects, and FIG. 02 shows it within Quebec and Labrador.

The deposit is magnetite. Magnetite is an iron oxide that is magnetic, so it can be pulled out of crushed rock with magnets. The rock averages 29.1 per cent iron. Magnetite ore is usually lower in grade than Pilbara ore, which is shipped at about 56 to 62 per cent iron after crushing and screening [R6]. The value is in the upgrade. The rock is ground to a fine powder and separated before it is sold, and what comes out is a concentrate of about 69 to 71 per cent iron [R1].

The updated study plans to mine and process 3.4 billion tonnes of ore over 40 years and feed the plant at about 100 million tonnes a year at full rate [R1]. About 95 per cent of that ore is Probable Ore Reserve. A Probable Ore Reserve is the part of a deposit that a study has shown can be mined and sold at a profit, on a level of confidence one step below the highest. The other 5 per cent is Inferred Mineral Resource, the least certain category, where the drilling is too wide to be sure of the tonnes and grade.
At full production the plan makes two products. One is 7.3 million tonnes a year of blast furnace concentrate at 69.1 per cent iron. The other is 18.6 million tonnes a year of direct reduction pellets [R1]. Direct reduction, or DR, is the route to steel that uses gas or hydrogen in place of coking coal. It needs very pure iron ore, and pellets are the hard balls that ore is formed into for that furnace (PLATE 01). The pellets would be made at Pointe-Noire near Sept-Îles on the St Lawrence River, about 620 kilometres south by rail.

Samso covered the July study in Iron Bear Resources (ASX: IBR) maiden PFS, and every Samso piece on the company is listed on the Iron Bear Resources company page. TABLE 01 sets the July study beside the November update. The company states that the key assumptions, including the prices, did not change between the two [R1].

The headline revenue assumption is a long-term price of US$120 a tonne for 65 per cent iron ore delivered to China. It is a forecast of the price over the life of the mine, not today's price. The study built it from Wood Mackenzie and other analyst forecasts and a review of studies published in 2025 and 2026, and states it in early-2026 dollars [R1]. On top of that the study adds quality premiums, giving US$152 a tonne for the concentrate and US$212.30 a tonne for the pellets, delivered to the customer [R1]. The model then raises the benchmark price by 2.5 per cent a year for inflation, and the pellet premium by 3 per cent a year, from 2026 through the life of the mine [R1].
The study's long-term price for 62 per cent ore is US$100.40 a tonne. The market price for that ore fell from US$97 to US$90 a tonne by 16 November 2026. The study says the July price assumptions were checked and left unchanged, and that the fall is not expected to change the long-term outlook [R1]. The study's long-term price for that ore is therefore about 12 per cent above the market price on 16 November, Samso's arithmetic.
2.00 — WHERE THE EXTRA US$2.6 BILLION OF NPV CAME FROM
Five changes to the plan, with prices unchanged
The company calls the work a value improvement process. It made five changes to the July plan and modelled them one after another, so each can be read on its own [R1]. FIG. 03 is the company's chart of the result.

The largest gain, US$915 million, came from keeping the plant full. Each section of a processing plant has a nameplate capacity, the rate it is designed for, and a short-term sprint capacity above that. The update cut the planned sprint margin from 15 per cent to between 5 and 10 per cent in the first six years. Once the mine reaches full rate in year 11, it feeds the plant at its rated capacity. The steady feed rate rises to between 92 and 103 million tonnes a year [R1]. Feeding more rock each year brings revenue forward and shortens the mine life from 44 years to 40.
The second largest, US$630 million, came from mining higher-grade rock first. In the first four years the plant now recovers 30 to 32 per cent of the rock it treats as concentrate, against about 29 per cent over the whole mine life [R1]. That share is called the mass yield. A higher mass yield means more saleable tonnes from the same amount of grinding.
The grinding circuit was redesigned. The July study crushed the rock with high-pressure grinding rolls, which squeeze it between two large rollers, ahead of ball mills, rotating drums that grind it with steel balls. The update replaces the rolls with autogenous mills, large rotating drums where the rock grinds itself. The ball mills and the final grind to 32 microns stay [R1]. That cut pre-production capital by about US$227 million and added US$524 million of NPV [R1]. The estimate for the tailings dam, which stores the ground waste left after the iron is separated, was updated, adding US$248 million of NPV, and the third processing line now starts in year 8 rather than year 9, adding US$291 million.
The study gives the build times for the three processing lines in two ways. The body of the study gives 5, 3.5 and 3.5 years, and JORC Table 1 at the back, the disclosure checklist the ASX reporting code requires, gives 5, 4 and 3 years [R1]. Both are quoted here as published.
None of the five changes touches the iron ore price. The NPV rose because the same orebody is planned to be mined and processed faster and at a lower capital cost.
The new grinding circuit is the newest part of the plan, so its cost is at an earlier stage. The study estimates it to AACE Class 5 for this release [R1]. AACE is the US cost engineering body whose classes describe how accurate an estimate is. The study gives the rest as Class 4, accurate to plus or minus 25 per cent [R1]. Class 5 is the concept-level grade, one step earlier. What we still need to know is whether the US$524 million of NPV from this change holds when the next study costs it in detail.
SAMSO TAKE The useful thing about this update is that the price deck did not move. Every dollar of the extra NPV comes from engineering choices that can be tested in the next study. Those choices still need to be proven. The plant has to run above its design rate in its early years and at full capacity for decades after that, and the new grinding circuit has to cost what the rough estimate says. The costs in the study are also today's costs. They look high against mines built 10 years ago. Even in today's money they are the highest here, and a decade of inflation has lifted the cost of building anything. Prices have risen over the same decade, and over time the two tend to settle into some balance. If a global recession becomes the conversation, prices would fall and costs would follow them. The costs Iron Bear is quoting would soften as well. Will the bankable study hold the throughput gain when the engineers have to guarantee it? |
3.00 — REAL AND NOMINAL IRR
Iron Bear's 17.9 per cent nominal is about 15 per cent in real terms
Every study works out its IRR from a table of cash flows, money going out to build the mine and money coming back from selling the product. FIG. 04 is Iron Bear's table drawn as a chart.

There are two ways to build that table. A real model keeps prices and costs flat at today's level for the whole life of the mine. A nominal model lets prices and costs rise with inflation every year. The second gives a higher IRR, because every dollar in it is measured in money that loses value each year. The IRR then carries the inflation rate inside it.
Iron Bear's model is nominal. The study lifts capital, operating costs and the 65 per cent benchmark price by 2.5 per cent a year, and lifts the DR pellet premium by 3 per cent a year [R1]. The 8 per cent discount rate is also nominal. Champion Iron's 2017 Bloom Lake study, by contrast, states that it used no inflation [R3]. Rio Tinto states that its Simandou IRR is real [R7]. Anglo American states the same for Quellaveco [R10].
Samso converted Iron Bear's IRR to real terms. When prices and costs all rise at one rate, one plus the real return is one plus the nominal return divided by one plus inflation. We divided 1.179 by 1.025, which gives 1.150. That is a real IRR of about 15.0 per cent. The same calculation turns the July figure of 15.2 per cent into about 12.4 per cent. This is Samso's calculation, not company guidance. It is approximate. The pellet premium in the model rises 0.5 percentage points a year faster than inflation, and that stays inside the 15.0 per cent. A model with every price held flat would give a little less.
The same calculation also works the other way. Champion's 33.3 per cent real IRR at Bloom Lake becomes about 36.6 per cent if 2.5 per cent inflation is added to it. Bringing the two onto one basis widens the gap between them.
An IRR is a rate, so it stays as it is when we move to today's money. What has to match is the basis it was calculated on, real or nominal. The dollar amounts in a study, the capital, the NPV and the price assumed, are what change with time, and section 4.00 brings Bloom Lake's dollar amounts forward to 2026.
4.00 — BLOOM LAKE IN TODAY'S DOLLARS
Champion Iron's 2017 restart study, brought forward to 2026 prices
Bloom Lake is an open-pit iron ore mine near Fermont in north-eastern Quebec, about 250 kilometres south of Iron Bear in the same belt (FIG. 01). An earlier owner built the mine and the concentrator, the plant that upgrades the ore. Champion Iron (ASX: CIA) bought the mothballed mine from Cliffs Natural Resources in April 2016 for a reported 10.5 million dollars [R15]. The source does not name the currency. Champion published a feasibility study for a restart on 16 February 2017 and restarted the mine in February 2018 [R4].
The 2017 study gave a post-tax NPV of C$984 million at an 8 per cent discount rate and a post-tax IRR of 33.3 per cent. It assumed capital of C$326.8 million, including C$157.2 million to upgrade the mine, and production of 7.4 million tonnes a year of 66.2 per cent iron concentrate over 21 years. The operating cost was C$44.62 a tonne delivered to a ship at Sept-Îles. The iron ore price used was US$78.40 a tonne for 66.2 per cent ore delivered to China, with no inflation [R3].
Samso brought those figures forward to October 2026. Canadian dollar amounts were lifted by the Canadian consumer price index, which rose from 129.7 in February 2017 to 170.4 in October 2026, an increase of 31.4 per cent [R18]. The US dollar price was lifted by the US consumer price index, which rose 38.3 per cent over the same months [R19]. TABLE 02 shows the result.

In today's money Champion's price assumption is about US$108 a tonne for 66 per cent ore. Iron Bear assumes US$120 for 65 per cent ore. The two studies start from similar price ground once inflation is taken into account. The large gap is in capital.
Champion spent about C$429 million in today's money to restart a plant that produces 7.4 million tonnes a year, which is about US$41 for each tonne of yearly capacity. Iron Bear plans to spend US$4.04 billion before first production for a first processing line of about 9.2 million tonnes a year, which is about US$449 a tonne once lifted to October 2026 prices [R1]. Bloom Lake's restart cost about a tenth as much per tonne because the plant, the tailings dam and the rail connection were already there. The two figures are therefore not a like-for-like comparison. Iron Bear has to build its plant and tailings dam from the start. It will use the existing rail line, adding a new loading loop and sidings [R1].
The 2019 Phase II study followed the same pattern. It assumed C$589.8 million to finish a second concentrator and double output to 15 million tonnes a year, at a post-tax IRR of 33.4 per cent [R4]. About C$1.2 billion had already been spent on that phase by the previous owner, as reported in 2020 [R16]. In today's money the Phase II capital is about C$737 million.
Bloom Lake's IRR is the return on buying a built mine cheaply and finishing it. For a greenfield project, one built where no plant exists, the closer guide in the district is Champion's Kami project, in section 6.00.
5.00 — HOPE DOWNS AND THE PILBARA BUILDS
What Rio Tinto and BHP spent on mines with no published IRR
Hope Downs is a group of mines in the Pilbara of Western Australia, owned in equal shares by Rio Tinto and Hancock Prospecting (FIG. 01). Hope Downs 1 started in 2007 and Hope Downs 4 in 2013 [R20]. Hope Downs 4 was budgeted at US$1.6 billion for 15 million tonnes a year, as reported at the time [R13]. In June 2025 the partners approved Hope Downs 2 at US$1.6 billion for 31 million tonnes a year [R20].
Samso searched Rio Tinto's releases and found no published IRR for Hope Downs 4 or Hope Downs 2. Section 8.00 sets out a Samso model of what the IRR may have been. BHP takes the same approach. It approved South Flank in June 2018 and described it as "a capital efficient project which offers attractive returns", without giving a number [R9].
The capital figures can still be compared. In today's dollars Hope Downs 4 cost about US$2.4 billion, or about US$163 for each tonne of yearly capacity. South Flank cost US$3.6 billion when it started in May 2021 for 80 million tonnes a year, about US$57 a tonne in today's money [R9]. The Western Australian Government lists more recent builds. Gudai-Darri cost A$4.3 billion for 43 million tonnes a year, Western Range A$3.0 billion for 25 million tonnes and Onslow Iron A$2.5 billion for 30 million tonnes [R6].
These are low numbers per tonne for two reasons. The ore is shipped after crushing and screening, with no grinding or separation plant. Most of them also feed into railways and ports the owners had already built. Onslow Iron is the exception. Mineral Resources built new infrastructure to reach the coast, and it came in at about A$83 a tonne of capacity [R6].
Pilbara ore and Iron Bear concentrate are different products. Pilbara fines, the finer crushed ore, sell at a discount to the 62 per cent benchmark. Iron Bear's concentrate is priced in its study at US$152 a tonne and its pellets at US$212.30 [R1]. A tonne of Iron Bear capacity is meant to earn more than a tonne of Pilbara capacity, and it costs much more to build.
6.00 — THE MAGNETITE AND DR FEED BUILDS
Iron Bridge, Kami and Simandou are the projects closest to Iron Bear
Iron Bridge is Fortescue's magnetite mine about 145 kilometres south of Port Hedland in the Pilbara. It was approved in April 2019 at US$2.6 billion to make 22 million tonnes a year of 67 per cent iron concentrate [R14]. It made its first concentrate in April 2023 at a final cost of US$3.9 billion [R8]. Against the approved plan of first ore in the first half of 2022 at US$2.6 billion [R14], that is about a year late and US$1.3 billion over budget, Samso's arithmetic. Fortescue has not published an IRR for it that Samso could find, and section 8.00 models one. In today's money Iron Bridge cost about US$198 for each tonne of yearly capacity.
FIG. 05 shows the mine, its 135 kilometre concentrate pipeline to Port Hedland and its water supply line.

Iron Bridge is the nearest built example of a large magnetite plant. Its capital rose by half between approval and first production.
Kami is Champion Iron's undeveloped magnetite project near Labrador City and Wabush, in the same province as Iron Bear and about 250 kilometres to its south. Its project study, released on 30 January 2024 as an update of the Kami feasibility study, planned 9.0 million wet tonnes a year of DR-grade concentrate above 67.5 per cent iron over 25 years [R5]. Wet tonnes include the water in the ore. It put capital at C$3.864 billion. It gave a post-tax IRR of 9.8 per cent on what Champion called conservative prices, and 14.8 per cent on the average 65 per cent benchmark price of the previous three years [R5]. Samso could not find a statement in the release on whether that IRR is real or nominal.
Kami is the closest comparison to Iron Bear. It is in the same province, would make iron concentrate for DR steelmaking, and its study was published in the last three years. Iron Bear plans to sell blast furnace concentrate and DR pellets, so the products are not the same. Kami's capital is about US$324 for each tonne of yearly capacity in today's money. Iron Bear's first stage is about US$449 on the same basis. Neither figure includes a pellet plant, but Iron Bear's first stage carries the tailings dam, rail loop and site services for all three stages. In September 2025 Nippon Steel and the trading house Sojitz took a combined 49 per cent of Kami, leaving Champion with 51 per cent [R17].
Simandou is in south-eastern Guinea. Rio Tinto describes it as the world's largest untapped high-grade iron ore deposit [R7]. Rio Tinto's Simfer joint venture put its capital at US$11.6 billion in December 2023 for a 60 million tonne a year mine, a 70 kilometre rail spur and a share of a 552 kilometre rail system and port co-developed with Winning Consortium Simandou and the Republic of Guinea [R7]. Rio Tinto gave the capital in nominal terms, so Samso has not lifted it for inflation. That is about US$193 for each tonne of yearly capacity.
Rio Tinto gave a post-tax real IRR of 11 to 13 per cent, based on average Wood Mackenzie and CRU prices for 65 per cent ore with a premium for DR product [R7]. The first ship left Guinea in December 2025 [R21].
Simandou, like Iron Bear, is a greenfield project that has to pay for new infrastructure to reach the sea. Simandou's partners built a new railway and port. Iron Bear plans to use existing railways owned by others and add new facilities at the port of Pointe-Noire [R1]. Iron Bear's real IRR of about 15 per cent, on Samso's conversion, is above Simandou's range.
7.00 — LARGE PROJECTS IN OTHER COMMODITIES
Jansen potash and Quellaveco copper show the size of the return the majors accept
Jansen is BHP's potash mine in Saskatchewan, Canada. Potash is a fertiliser mineral mined from deep underground beds. BHP approved Stage 1 in August 2021 at US$5.7 billion for about 4.35 million tonnes a year, and gave a post-tax nominal IRR of 12 to 14 per cent [R11]. That IRR left out the spending on the shafts and essential services. BHP put the capital already invested at US$4.5 billion. BHP said that including it would give a much lower return.
In January 2026 BHP raised the Stage 1 cost to US$8.4 billion, said production would be about 4.15 million tonnes a year, and cut the IRR to 7.9 to 9.1 per cent [R12]. The cost rose about 47 per cent, Samso's arithmetic, and the IRR fell by four to five percentage points.
Quellaveco is Anglo American's copper mine in southern Peru. Anglo American approved it in July 2018 at US$5.0 to 5.3 billion for about 300,000 tonnes a year of copper in its first ten years. It gave a real post-tax IRR of more than 15 per cent [R10].
These two give a sense of the returns large miners approve. Quellaveco and Simandou were approved on real IRRs in the low to middle teens. Jansen was approved on a nominal IRR in the low teens, on a project expected to run for decades.
8.00 — THE COMPARISON SIDE BY SIDE
Iron Bear's return beside built projects, published and modelled
FIG. 06 sets the published and modelled IRRs side by side, coloured by the basis each was calculated on. The modelled figures are for the three mines with no published IRR. FIG. 07 sets the capital cost for each tonne of yearly iron ore capacity side by side, with every figure brought to US dollars at October 2026 prices.

On return, Iron Bear's updated study is in the same range as projects that were built. Its real IRR of about 15 per cent, on Samso's conversion, is above Simandou's 11 to 13 per cent and similar to Quellaveco's more than 15 per cent. It is above the upper end of Kami's range, whose basis Champion did not state. It is well below Bloom Lake, whose IRR came from restarting a plant that a previous owner had paid for.

On capital, three features of the project explain why Iron Bear is the highest per tonne in FIG. 07. Magnetite at 29 per cent iron has to be ground very fine, and the plan uses nine large autogenous mills, each drawing about 19.5 megawatts. The full build includes two pellet plants and new port facilities at Pointe-Noire, although the Stage 1 figure of US$449 a tonne has neither. The site is also in sub-Arctic Labrador, where construction is slower and every building needs heating [R1].
The two measures are linked. A project that costs more per tonne needs a higher price per tonne to earn the same return, and Iron Bear's study assumes quality premiums for its concentrate and DR pellets. The return depends on those premiums holding for 40 years.
A Samso model for three mines with no published IRR
Rio Tinto, BHP and Fortescue have not published an IRR for Hope Downs 4, South Flank or Iron Bridge. What follows is a theoretical model built by Samso from released data.
Samso built one simple cash flow model and ran every mine through it on the same rules. Each mine gets its own capital cost, build years, tonnes, operating cost and royalty. All of them get the same treatment for tax and inflation. Every dollar is in October 2026 money, so the results are real IRRs and are on the same basis as Simandou, Quellaveco and Samso's 15 per cent for Iron Bear. TABLE 03 lists the inputs and where each came from. The operating costs come from the cost figures BHP, Rio Tinto and Fortescue published [R25][R27][R14][R33], and the royalty rates from the Western Australian Government [R34].

The price is the input that moves the answer most, so each mine was run in two ways. One uses the iron ore price that actually applied in each year the mine has run, from the IMF series [R28], and Iron Bear's long-term price from 2026 on. The other uses Iron Bear's long-term price for every year [R1]. The second puts every mine on the same price ground as the Iron Bear study.
The Pilbara mines sell their ore below the benchmark price. BHP received an average of US$82.13 a wet tonne in the year to June 2025 [R26], when the 62 per cent benchmark averaged about US$103 a dry tonne delivered to China [R28]. That is about 80 per cent of the benchmark. The gap covers the lower grade, the water in the ore and the freight to China. Samso applied that ratio to both Pilbara mines. For Iron Bridge, Fortescue received 101 per cent of the 65 per cent benchmark in the year to June 2026 [R30].
Samso also ran its model on Iron Bear's study inputs, as a check on the method. The study's 17.9 per cent includes the income tax holiday set out in section 9.00. Without it the study gives 16.8 per cent nominal [R1], about 14.0 per cent real on Samso's conversion. The model has no tax holiday and gives 12.4 per cent on the same inputs. It reads about 1.6 percentage points below the company's model on Iron Bear, and the other results may carry a similar error. TABLE 04 gives the results for every case.

South Flank comes out at about 46 per cent on actual prices and 37 per cent on Iron Bear's price. Two things drive that. Its haematite ore needs only crushing and screening, and BHP spent about US$57 for each tonne of yearly capacity, because the rail line, the port and much of the hub already existed. Even if every South Flank tonne paid an extra US$10 towards rail and port capital, a Samso assumption, the IRR would stay above 40 per cent.
Hope Downs 4 comes out at about 25 per cent on actual prices and about 19 per cent on Iron Bear's price. It started production in 2013, just before the price fell from about US$135 a tonne to under US$60 by 2015 [R28], and on this model it still returns in the high teens or better. With the US$10 a tonne infrastructure charge it falls to about 21 per cent.
Iron Bridge gives the widest range. Fortescue approved it in April 2019 on US$2.6 billion of capital, first ore in the first half of 2022, full rate within 12 months and a C1 operating cost of US$30 to US$35 a dry tonne, including a fee for port access [R14]. On that plan the model gives about 25 per cent. On what has happened since, it gives about 4 per cent.
The capital rose to US$3.9 billion and the first concentrate came in April 2023 [R8]. Shipments were 1.2 million tonnes in the year to June 2024, 7.1 million tonnes in the next year and 9.0 million tonnes in the year to June 2026, against a nameplate of 22 million [R29][R31][R32].
Fortescue holds 69 per cent of Iron Bridge [R29] and expected its share of the operating cost to be about US$650 million in the 2026 financial year [R33]. For the whole mine that is about US$105 a tonne at 9.0 million tonnes, Samso's arithmetic. Fortescue has guided to about US$900 million for its share in the 2027 financial year and to US$60 to US$70 a wet tonne in the medium term [R29]. It also expects to record an impairment on Iron Bridge of about US$525 million after tax [R29].
This model gives the reader a scale for Iron Bear's figure. On it, a brownfield haematite mine, one using rail and port that already exist, returns a real IRR from the high teens to the 40s. A greenfield magnetite plant comes out at about 25 per cent on its approved plan and about 4 per cent on its record so far. Iron Bear is a greenfield magnetite project, so Iron Bridge is the closer comparison. Its study gives about 15 per cent real, between the two Iron Bridge cases.
HOW SAMSO MADE THE COMPARISON Capital costs were taken from each company's release where one was available, from trade press for Hope Downs 4 [R13], and from the Western Australian Government's July 2026 iron ore profile for the Pilbara builds [R6]. Canadian dollar figures were lifted from the month of the study to October 2026 by the Canadian consumer price index [R18] and converted at C$1.4256 to US$1, the US Federal Reserve rate for 13 November 2026 [R22]. US dollar figures were lifted by the US consumer price index [R19]. Consumer prices are a rough guide to mine construction costs. Mine construction costs may have risen faster than consumer prices between 2021 and 2023, the period of the Iron Bridge and Jansen overruns. If so, the older figures in FIG. 07 are more likely to understate what the same project would cost to build today than to overstate it. |
9.00 — WHAT THE STUDY LEAVES OUTSIDE ITS NUMBERS
The power line, the tax holiday and the rail access
Three items in the study are outside the headline numbers and could move them. Each is disclosed in the study.
The power line. The mine needs about 490 megawatts at full rate, supplied from the Churchill Falls hydroelectric station about 342 kilometres away [R1]. The study assumes a third party builds, owns and finances the transmission lines, at a cost of about US$3.0 billion, and that Iron Bear pays for them through a delivered power price of US$0.148 a kilowatt-hour. The price at the power station is US$0.0315. The US$3.0 billion is therefore not in the capital figure.
The study states that if Iron Bear funded the lines itself, pre-production capital would rise by about US$1.29 billion, the IRR would fall by 1.2 to 1.4 percentage points, and the post-tax NPV would rise by 4 to 6 per cent [R1]. The power purchase agreement is one of the agreements still to be signed.
The tax holiday. The model assumes no corporate income tax for about the first eight years of production [R1]. The study states that the company has discussed this with the Newfoundland and Labrador Government, that no agreement has been reached and that there is no certainty one will be granted. Without the holiday the post-tax NPV is US$10.4 billion and the IRR is 16.8 per cent nominal, which is about 14.0 per cent real on Samso's conversion.
The rail access. Concentrate would travel about 620 kilometres over railways owned by other operators, shown in FIG. 08. The study names access fees on those lines as the main commercial risk of the rail route and says long-term access agreements are needed before a decision to mine [R1].

The study also records two technical items still to be proven at scale. The concentrate dryer, a design called BALF that dries without heat, has been tested in a unit of about 5 tonnes an hour and is not yet proven for iron ore. The variability test work, which checks how different parts of the orebody behave in the plant, was not finished within the study [R1]. The next study has to complete both.
10.00 — THE STUDY AGAINST THE SHARE PRICE
Market value, cash and the study NPV
Iron Bear shares closed at 1.8 cents on 20 November 2026 [R23]. With about 1.108 billion shares on issue [R35], that is a market capitalisation of about A$20 million. The chairman's letter of 18 November states the company held A$13.6 million in cash at the end of September 2026 [R24].
At the study's exchange rate of 65 US cents to the Australian dollar, the post-tax NPV of US$11.6 billion is about A$17.9 billion. The market capitalisation is about 0.11 per cent of that figure. This is Samso's arithmetic and not a valuation.
The market price is likely to reflect the steps still ahead. An NPV assumes the mine is funded, approved and built as planned. The study states that about US$50 million is needed to reach a decision to mine, and then about US$4.0 billion to build the first stage [R1]. The environmental assessment alone is expected to take up to six years. The company's development plan, reproduced in FIG. 09, puts a decision to mine after December 2029, and its risk register names first ore on a ship in 2035 as the target.

Vale, which was funding the study, declined to go on to the second phase of its development agreement in September 2026, and Iron Bear kept 100 per cent of the project [R24]. In his letter of 18 November, chairman Simon Lill wrote, "We are prioritising cash preservation to navigate volatile capital markets and which translates into a reduced cash burn rate moving forward. I am confident that we will be able to source additional capital to assist the development of this exciting Project." [R24] The study says projects of this size are usually developed with strategic, offtake or project finance partners, and that funding the capital could materially reduce the company's ownership [R1].
SAMSO TAKE In October I said Iron Bear still needed a big brother, and that on the potential in the ground against the price of the company, it may be the cheapest mineral asset on the ASX [R2]. The company was worth about A$25 million then. It is worth about A$20 million now, with a better study. The market values the company on what it can see today. The mine would sell into a market about 5 to 10 years away, with the study targeting first ore on a ship in 2035 [R1]. Today's iron ore narrative is weak, and so is the forecast. That may turn out close to what happens. Global investors have also seen the narrative change many times before a project reaches production. The update makes the project easier to present to a partner. The return is now in the range of projects the majors have built. The capital per tonne is still the highest in this comparison, and that is the number a partner will look at first. Kami found its partners with a lower IRR. Can Iron Bear find one on a higher IRR and a bigger cheque, while keeping more than the 25 per cent Vale would have left it? |
11.00 — THE CASE AGAINST THE COMPARISON
A study IRR and a built mine's IRR are not the same kind of number
THE STANDING COUNTERARGUMENT The published IRRs compared here came from feasibility-level studies or at the point a board approved spending the money. Iron Bear's is a pre-feasibility figure, one study stage earlier. The study gives its capital as accurate to plus or minus 25 per cent, its tailings estimate to plus 50 and minus 30 per cent, and its grinding circuit to a rougher grade still [R1]. Iron Bridge's capital rose 50 per cent and Jansen's 47 per cent after approval, when their estimates were already more advanced than Iron Bear's is now [R8][R12]. The study's sensitivity table shows how much rides on the inputs. A 20 per cent lower iron ore price cuts the NPV from US$11.6 billion to US$6.8 billion. A 20 per cent higher discount rate cuts it to US$7.6 billion [R1]. The premiums for DR pellets are an assumption about demand. The study puts global DR pellet demand at about 180 million tonnes a year in 2024, growing to 447 million tonnes by 2050 [R1]. That growth depends on steelmakers building the DR plants that have been announced. The other side is also in the study. The prices did not change between July and November, so the gains came from changes to the plan. The tax assumption applies the higher Newfoundland and Labrador rate to income that would partly be taxed at Quebec's lower rate [R1]. That makes the modelled tax higher than it may turn out to be. |
SAMSO TAKE Put on one basis, Iron Bear's return is competitive with projects that were built. Its capital per tonne is not. The next study has to show that the throughput and the grinding savings hold when an engineer has to guarantee them. If they do, does the market keep pricing the company at about a tenth of one per cent of its study? One has to remember that Iron Bear is selling into a market 5 to 10 years away. The iron ore narrative now is low, and the projection is low. However, coming away from the SMM conference in Sydney recently, the demand for iron ore in China is still at a minimum. The global narrative for iron demand is significantly more apparent than what I'm hearing coming out of the SMM conference. We all know that China is in a debt issue. However, as many narratives say, one would be very foolish to bet against the Chinese economy. If one compares the outlook for iron with the current narrative, it would be safe to say that you're not far from what could be reality. However, as global investors have seen many times over, the winds of change could be just around the corner. As iron ore is a staple diet for the global economy, one cannot develop without this simple commodity. The other point is that if Iron Bear can make good its direct reduction abilities, the game completely changes again. |
THE VOCABULARY, IN PLAIN ENGLISH Magnetite An iron oxide mineral that is magnetic, so it can be separated from crushed rock with magnets. Iron Bear's rock is about 29 per cent iron and is upgraded to a concentrate of about 69 to 71 per cent. Concentrate The fine iron-rich powder left after the rock is ground and the waste minerals removed. Direct reduction (DR) pellets Hard balls of very pure iron ore fed to a direct reduction furnace, which uses gas or hydrogen in place of coking coal to make iron. Blast furnace (BF) concentrate The concentrate product sold to steelmakers using the conventional coal-fired blast furnace route. Pre-feasibility study (PFS) The middle of the three study stages before a mine is built. Costs are estimated to about plus or minus 25 per cent. The next stage, a bankable feasibility study, is what lenders and boards approve spending on. AACE Class 4 and Class 5 Accuracy grades for cost estimates set by AACE International, a cost engineering body. Class 4 is a pre-feasibility grade of plus or minus 25 per cent. Class 5 is a rougher concept grade. Probable Ore Reserve The part of a deposit a study has shown can be mined and sold at a profit, at the lower of the two confidence levels for reserves. Inferred Mineral Resource The least certain category of resource. The drilling is too widely spaced to be sure of the tonnes and grade. Mass yield The share of the rock fed to the plant that comes out as saleable concentrate. Autogenous (AG) mill A large rotating drum in which the rock grinds itself, without steel balls. Nameplate and sprint capacity Nameplate is the rate a plant is designed to run at. Sprint is a higher rate it can sustain for shorter periods. Real and nominal IRR A real IRR is worked out with prices and costs held flat. A nominal IRR lets them rise with inflation, which gives a higher figure for the same project. Capital per tonne of yearly capacity The cost to build a project divided by the tonnes it is designed to produce each year. It allows projects of different sizes to be compared. Decision to mine The point at which the owner commits to build, normally after a bankable feasibility study, permits and funding are in place. FOB and CFR FOB, free on board, is the cost or price with the product loaded on the ship. CFR, cost and freight, includes shipping to the customer's port. Labrador Trough A belt of iron-rich rock about 1,600 kilometres long running through Quebec and Labrador, mined for iron ore since 1954. Potash A potassium mineral mined from deep underground beds and sold as fertiliser. |
12.00 — REFERENCES AND SOURCES
Where every figure comes from
Each entry carries an identifier, [R1] to [R35], and the same identifier appears in the text where the source is used. FIG. 02, FIG. 03, FIG. 04, FIG. 08, FIG. 09 and PLATE 01 are reproduced from Iron Bear's public ASX release with attribution. FIG. 05 is reproduced from Fortescue's public ASX release of 2 April 2019 with attribution. FIG. 01, FIG. 06 and FIG. 07 and all four tables are original Samso work on sourced data. TABLE 03 and TABLE 04 are a theoretical model. Market-sensitive numbers are as at their stated dates and are refreshed before publication.
[R1] Iron Bear Resources Limited, "Updated Iron Bear Project PFS", ASX release 23 November 2026, 146 pages, including JORC Table 1. (read in full)
[R2] Samso, "Green Iron in Labrador. Is Iron Bear Still in Play?", Samso Insights, October 2026.
[R8] Fortescue, "Fortescue's Iron Bridge commences high grade magnetite production", 30 April 2023.
[R10] Anglo American, "Anglo American approves Quellaveco copper project for development", 26 July 2018.
[R11] BHP, "BHP approves investment in Jansen Stage 1 potash project", 17 August 2021.
[R12] BHP, "Update - Jansen Stage 1 Potash Project", 20 January 2026.
[R29] Fortescue, "June 2026 Quarterly Production Report", ASX release 31 July 2026.
[R31] Fortescue, "June 2024 Quarterly Production Report", ASX release 25 July 2024.
[R32] Fortescue, "June 2025 Quarterly Production Report", ASX release 24 July 2025.
[R34] Government of Western Australia, "Mineral royalties in WA" fact sheet, September 2025.
Cover photo. Iron Bear DR pellets, bulk production sample. Iron Bear Resources, PFS Update, ASX release 23 November 2026, Figure 24, page 63.