Pivotal Metals Limited (ASX: PVT) is a copper and nickel explorer and developer in Québec, Canada. It listed on the ASX on 26 July 2018 (ASX company page) and was called Rafaella Resources Ltd, code RFR, until 29 November 2022 (ASX code change list). Its main asset is the Horden Lake Project, which it owns 100 per cent. Horden Lake has a Mineral Resource of 52.4 million tonnes at 0.56 per cent copper (resource announcement, 7 July 2026) and a Scoping Study published on 29 September 2026. Pivotal also drilled copper, nickel and gold targets at its Belleterre Projects in 2026. It held A$2.4 million in cash at 30 September 2026 (Appendix 5B, lodged 30 October 2026). Samso had published six pieces on the company at 18 November 2026.

ASX code: PVT. Full legal name: Pivotal Metals Limited. Managing Director and Chief Executive Officer: Ivan Fairhall. The other directors are Simon Gray, the non-executive chairman, and Robert Wrixon and Daniel Rose, both non-executive directors (annual report, lodged 18 September 2026). Pivotal held A$2.4 million in cash at 30 September 2026. The quarterly cash flow report lists no loan facilities (Appendix 5B, lodged 30 October 2026).

Pivotal Metals projects

Pivotal has two projects in Québec, Canada.

A Mineral Resource is a company's estimate of the material in the ground that has reasonable prospects of eventual economic extraction. It is stated as tonnes and grade, the amount of metal in the rock. The JORC Code, the Australasian reporting code, has three confidence categories. Measured is the highest, Indicated is the middle one and Inferred is the lowest, where the drill holes are furthest apart.

  • Horden Lake Project, about 10 kilometres west of the James Bay Highway and 130 kilometres north of the town of Matagami. Copper, nickel, gold, silver, palladium, platinum and cobalt. A wholly owned subsidiary holds 100 per cent of the 1,032-hectare claim package, which is on Crown land (scoping study announcement, 29 September 2026). The project is subject to two separate 1 per cent net smelter return royalties (annual report, note 22, lodged 18 September 2026). A net smelter return, or NSR, is the revenue a mine receives for its metal after smelter charges.
  • Belleterre Projects, about 85 kilometres south of Rouyn-Noranda. Copper, nickel, platinum group metals and gold. Pivotal put its wholly owned ground there at 160 square kilometres (ASX announcement, 2 July 2026) in three areas called Midrim-Alotta, Lorraine and LaForce. Some of the claims carry royalties of up to 2.5 per cent (annual report, note 22). In the September 2026 quarter Pivotal took an option to earn 100 per cent of the adjoining Bambino property, 3,320 hectares. The company says the option increased its footprint by 25 per cent, and the quarterly report gives the package as 199 square kilometres (quarterly report, lodged 30 October 2026).

The Horden Lake Mineral Resource

Pivotal reported an enlarged Mineral Resource for Horden Lake on 7 July 2026. The estimate is 52.4 million tonnes at 0.56 per cent copper, 0.17 per cent nickel, 10.2 grams of silver per tonne and 0.14 grams each of gold and palladium per tonne. Pivotal converts the other metals into copper using assumed prices and recoveries, and calls the result copper equivalent. That figure is 1.05 per cent. Of the total, 24.3 million tonnes is Measured and Indicated and 28.1 million tonnes is Inferred. The estimate was prepared by independent consultants and rests on 223 diamond drill holes. Diamond drilling cuts a solid core of rock (resource announcement, 7 July 2026).

The resource counts rock above a cut-off, the lowest value included. Pivotal sets it by the NSR value of each tonne. About 45.5 million tonnes sits inside an open pit shell, the outline of a pit that could be dug from the surface, at a cut-off of US$25 a tonne. The rest lies outside the shell at a cut-off of US$65 a tonne. The copper equivalent uses a copper price of US$11,000 a tonne and a copper recovery of 90 per cent. Horden Lake has no Ore Reserve, the part of a resource that a study has shown can be mined economically (resource announcement, 7 July 2026, and scoping study announcement, 29 September 2026).

Pivotal reported a second round of processing tests on 1 September 2026. Flotation grinds the rock and uses air bubbles to lift the metal-bearing minerals into a concentrate. The tests were run at a laboratory on 2 kilogram charges made up from drill core. A locked cycle test repeats the flotation steps to imitate a working plant. The second such test recovered 90.5 per cent of the copper into a concentrate grading 25.7 per cent copper. It recovered 36.2 per cent of the nickel into a separate nickel concentrate (ASX announcement, 1 September 2026).

At the average grades of the in-pit resource, Pivotal models recoveries of 92 per cent for copper and 46 per cent for nickel. The company says nickel recovery improves as sulphur falls, and that the test sample held 6.5 per cent sulphur against 3.6 per cent in the resource (ASX announcement, 1 September 2026).

The Horden Lake Scoping Study

Pivotal published a Scoping Study for Horden Lake on 29 September 2026. That is the first and least detailed of three study levels. The company gives its accuracy as minus 30 to plus 50 per cent.

The study plans one open pit feeding a plant that treats 3.5 million tonnes a year. The mine plan delivers 34 million tonnes of mill feed over 11 years, with 7.9 tonnes of waste for each tonne of feed. Payable metal over the life of the plan is 160,000 tonnes of copper and 20,000 tonnes of nickel.

Pre-production capital is put at A$428 million, including A$75 million of contingency. The study assumes a Canadian tax credit that would bring that to A$411 million. Operating costs are A$49.3 a tonne of mill feed. The all-in sustaining cost is US$1.00 a pound of copper after credits for the other metals, at an assumed copper price of US$5.50 a pound. That measure covers producing each pound and keeping the mine running, and leaves out the cost of building it (scoping study announcement, 29 September 2026).

About 30 per cent of the plan's NSR value comes from Inferred resources. The company says about 86 per cent of the material scheduled in the capital payback period is Indicated or higher. It cautions that Inferred resources carry lower geological confidence, and that there is no certainty they will be upgraded or that the production target will be realised. It also says the study is not sufficient to support an Ore Reserve. Pivotal believes it has a reasonable basis to expect it can fund the more than A$400 million needed, and says there is no certainty it will (scoping study announcement, 29 September 2026).

No environmental or statutory approvals have been sought. The project would be assessed under the environmental and social impact process of the James Bay and Northern Québec Agreement, which provides for Cree participation. Pivotal expects two summer seasons of baseline studies before it applies, then a review of 12 to 24 months. The site lies within a woodland caribou calving range (scoping study announcement, 29 September 2026). Pivotal plans Pre-Feasibility Study engineering in 2027 and has appointed an adviser to assess non-equity financing (quarterly report, lodged 30 October 2026). No decision to build has been announced.

Belleterre drilling

Pivotal reported the first results from its Belleterre drill program on 10 June 2026. Many targets come from electromagnetic and induced polarisation surveys, which detect rock that conducts or holds an electrical charge, as sulphide minerals do.

At Alotta, one diamond drill hole returned 21.8 metres at 1.27 per cent nickel and 1.03 per cent copper from 73 metres. Three holes drilled further out returned intervals of 2.4 to 3.7 metres at 0.17 to 0.46 per cent copper. One hole was abandoned, and a hole at Midrim East met sulphides that the company says were not materially mineralised. These are lengths measured down the hole. The announcement says it is not known how they relate to the true thickness of the mineralised zone (ASX announcement, 10 June 2026).

At Shanty Lake, a 679-metre hole returned no significant assay. A follow-up survey down the hole indicates it passed beneath the conductor, which remains untested (quarterly report, lodged 30 October 2026). At Lorraine Mine East, Pivotal drilled five holes for 988 metres. The best assay from the first three was 2.4 metres at 0.18 per cent copper from 154 metres, and the announcement's JORC table records no significant intersection. Pivotal expected assays from the last two holes by early December 2026 (ASX announcement, 30 October 2026). None had been announced at 18 November 2026.

Pivotal Metals cash and funding

Pivotal raised A$5.4 million in the year to 30 June 2026 (annual report, lodged 18 September 2026). The Appendix 5B divides the cash by the quarter's outgoings of A$1.0 million and gives 2.4 quarters of funding (Appendix 5B, lodged 30 October 2026).

The directors say they believe the company can raise more equity and reduce discretionary spending where necessary (annual report, note 1(b), lodged 18 September 2026).

Every Samso piece on Pivotal Metals

Six published pieces as at 18 November 2026, grouped by Samso product. Newest first in each group. Dates are Perth dates.

Samso News

Samso's most recent piece is dated 9 March 2026. Since then Pivotal has reported its first Belleterre drill results, the enlarged Horden Lake resource and the Scoping Study.

Questions people ask about Pivotal Metals (ASX PVT)

What does Pivotal Metals do? It explores for copper, nickel, gold and platinum group metals in Québec, Canada, and is studying a possible mine at Horden Lake, its main project, which it owns 100 per cent. It has no mine in production.

Was Pivotal Metals formerly Rafaella Resources (ASX RFR)? Yes. The ASX code change list shows Rafaella Resources Ltd (ASX RFR) became Pivotal Metals Limited (ASX PVT) on 29 November 2022.

What is the Pivotal Metals share price? The ASX website shows the PVT share price. This page has no live price.

What is the latest announcement from Pivotal Metals? As at 18 November 2026 the most recent announcements were lodged on 30 October 2026. They were the September quarter report and an exploration update on Belleterre.

Does Pivotal Metals have a Mineral Resource? Yes. Horden Lake has 52.4 million tonnes at 0.56 per cent copper and 0.17 per cent nickel, reported on 7 July 2026. Counting the other metals, Pivotal puts it at 1.05 per cent copper equivalent.

Is Pivotal Metals worth looking at? This page gives no buy, sell or hold call, price target or valuation. Horden Lake has a Mineral Resource, and 24.3 million of its 52.4 million tonnes is Measured and Indicated. The pre-production capital of A$428 million is not funded, and no approvals have been sought. Pivotal held A$2.4 million in cash at 30 September 2026. Samso had published no research workup on Pivotal Metals at 18 November 2026. The most recent Samso piece is the Samso News article of 9 March 2026.

Disclosure

Samso holds no shares in Pivotal Metals at 17 November 2026.

This page is general information only.

Depth over hype.

Samso company research pages are independent research commentary for general information only. Nothing on this page is financial product advice, and it does not take into account any reader's objectives, financial situation or needs. Figures are drawn from public sources believed reliable at the stated dates but are not guaranteed, and market-sensitive numbers change daily. Samso or associated parties may hold positions in, or have commercial arrangements with, companies mentioned. Seek professional advice before making investment decisions. © Samso 2026, samso.com.au

Page last reviewed 18 November 2026.

bottom of page