Chalice Mining Limited (ASX: CHN) is a mineral company based in Perth. It listed on the ASX on 24 March 2006 (ASX company page). Its main asset is the Gonneville Project, about 70 kilometres north-east of Perth, which it owns 100 per cent (annual report, lodged 29 September 2026). Chalice discovered the palladium, platinum, nickel, copper and cobalt deposit there in 2020. It reported an Ore Reserve of 260 million tonnes with a pre-feasibility study on 8 December 2025 (quarterly report, lodged 27 October 2026). It also explores for copper and gold. It held A$44.7 million in cash at 30 September 2026 (Appendix 5B, lodged 27 October 2026). Samso had published 3 pieces covering the company at 17 November 2026.
ASX code: CHN. Full legal name: Chalice Mining Limited. Managing Director and Chief Executive Officer: Alex Dorsch. At 17 November 2026 the other directors are Derek La Ferla, the non-executive chair, and Garret Dixon and Richard Hacker, both non-executive (ASX company page, read 17 November 2026). Mr La Ferla is to retire at the close of the annual general meeting on 20 November 2026. Ross Carroll is proposed as chair, with Gerard Rheinberger and Soolim Carney as non-executive directors, subject to shareholder approval (ASX announcement, 12 October 2026). Chalice held A$44.7 million in cash at 30 September 2026. The quarterly cash flow report lists no loan facilities (Appendix 5B, lodged 27 October 2026).
Chalice Mining projects
Chalice has one development project, Gonneville, and a spread of exploration ground. A Mineral Resource is a company's estimate of material in the ground that has reasonable prospects of eventual economic extraction. It is reported as tonnes and grade under the JORC Code, the Australasian reporting code. Grade is the amount of metal in the rock. Chalice adds palladium, platinum and gold into one figure it calls 3E, in grams per tonne. The code has three confidence categories, Measured the highest, then Indicated, then Inferred. An Ore Reserve is the part of the Measured and Indicated resource that a study has shown can be mined economically. Its categories are Proved and Probable.
- Gonneville Project, about 70 kilometres north-east of Perth. Palladium, platinum, gold, nickel, copper and cobalt. Chalice owns 100 per cent and owns the farmland over the deposit (annual report, lodged 29 September 2026). The Mineral Resource is 660 million tonnes at 0.79 grams per tonne 3E, 0.15 per cent nickel, 0.083 per cent copper and 0.015 per cent cobalt. Of that, 2.9 million tonnes is Measured, 400 million tonnes is Indicated and 250 million tonnes is Inferred. The estimate is dated 23 April 2024 (quarterly report, lodged 27 October 2026).
- Gonneville Ore Reserve is 260 million tonnes at 0.86 grams per tonne 3E, 0.16 per cent nickel, 0.098 per cent copper and 0.017 per cent cobalt, containing 7.1 million ounces of 3E. Of that, 2.5 million tonnes is Proved and the remainder is Probable. It is dated 8 December 2025 and used a palladium price of US$1,050 an ounce (quarterly report, lodged 27 October 2026). The reserve is limited to the Measured and Indicated resource inside the planned open pit (annual report, lodged 29 September 2026). The Mineral Resource figures above include the Ore Reserve (pre-feasibility study announcement, 8 December 2025).
- Warrego North Copper-Gold Project, in the Tennant Creek Mineral Field, Northern Territory. Chalice's interest is 51 to 100 per cent, depending on the licence (quarterly report, lodged 27 October 2026).
- Goomalling Copper Project, in the Western Australian Wheatbelt. Chalice owns some licences outright. On three others it has an earn-in agreement with Northam Resources, a right to earn up to a 70 per cent joint venture interest (tenement schedule in the quarterly report, lodged 27 October 2026).
The resource counts rock above a cut-off, the lowest value included. Chalice sets it by net smelter return, the revenue expected from a tonne of rock after allowing for metal recoveries, royalties, transport and smelter charges. It is A$25 a tonne inside the pit shape and A$110 a tonne for the underground part (quarterly report, lodged 27 October 2026).
Gonneville Project, the December 2025 pre-feasibility study
Chalice released a pre-feasibility study on Gonneville on 8 December 2025. A pre-feasibility study is the second of three study levels. The plan is an open pit mine, dug from the surface, built in two stages with a modelled life of 23 years. Stage 1 runs for four years and treats 1 million tonnes of oxide ore and 4 million tonnes of sulphide ore a year. Oxide ore is the weathered rock near surface and sulphide ore is the fresh rock beneath. Stage 2 lifts sulphide processing to 12 million tonnes a year from year 5 (annual report, lodged 29 September 2026).
The study's production target, its planned output, for Stage 1 is about 151,000 ounces of 3E a year, with 3,200 tonnes of nickel and 5,200 tonnes of copper. For Stage 2 it is about 238,000 ounces of 3E, 7,700 tonnes of nickel and 8,700 tonnes of copper a year. Measured resources make up 1 per cent of the target, Indicated 93 per cent and Inferred 6 per cent. Chalice cautions that Inferred resources carry a low level of geological confidence. It says there is no certainty that further exploration will upgrade them or that the production target based on them will be realised (annual report, lodged 29 September 2026).
The plant would grind the sulphide ore and use flotation, where air bubbles lift the metal-bearing sulphide minerals into a concentrate. It would make a copper concentrate and a nickel concentrate for sale to smelters, the plants that recover the metal, each carrying precious metals. What is left after flotation would go, with the oxide ore, to a leach, where a cyanide solution dissolves the precious metals. They are recovered as doré, an unrefined bar of mixed precious metals (pre-feasibility study announcement, 8 December 2025).
The study puts the all-in sustaining cost at US$370 for each ounce of 3E over the open pit life. That measure is the cost of producing an ounce, including the ongoing capital needed to keep a mine running. Chalice calculates it after subtracting nickel, copper and cobalt revenue and before royalties, so the result depends on the prices of those three metals. The base case assumed US$1,300 an ounce for palladium. The study estimates capital of A$820 million to build Stage 1 and A$840 million for the Stage 2 expansion, each including contingency. It gives the accuracy of the cost estimate behind the Ore Reserve as plus or minus 25 per cent (pre-feasibility study announcement, 8 December 2025).
Chalice is working towards a final investment decision, the board's decision to build, which it targets for the first half of 2028. Funding is still to be secured. The company aims to source 60 to 70 per cent of the pre-production funding from export credit agencies, the government-backed lenders that support export projects, or sovereign debt. Gonneville needs State and Commonwealth environmental approvals, which the company expects to set the timetable. The deposit is held under exploration licences, and Chalice expects to apply for a mining lease, the title needed to mine, in the first quarter of 2027 (quarterly report, lodged 27 October 2026).
Gonneville feasibility study and pilot plant
Chalice began a definitive feasibility study, the most detailed study level, in January 2026. It expects to complete the study in the second half of 2027. A pilot plant started in November 2026. It is a laboratory-scale run of the full process in continuous operation, using about five tonnes of fresh sulphide ore. The feed grades 1.7 grams per tonne 3E, 0.33 per cent nickel and 0.28 per cent copper. Chalice describes it as representative of early plant feed, and it is richer than the Ore Reserve average. First results from the flotation stage are expected in early 2027 (ASX announcement, 11 November 2026).
Warrego North and Goomalling drilling
Chalice drilled both projects in 2026 using reverse circulation drilling, shortened to RC, which returns rock chips. The company describes each program as a first-pass or reconnaissance test.
At Warrego North it drilled 16 holes and had assays, the laboratory results, for eight of them by 2 November 2026. All six holes at the Kestrel prospect intersected copper over about 500 metres of strike, the horizontal length of the zone. The first hole returned 27 metres at 0.42 per cent copper and 4.83 grams of gold per tonne from 78 metres. About 87 per cent of that gold sits in a 2-metre interval grading 56.7 grams per tonne. The company says coarse gold, gold in larger grains, may be present and that its influence on single high-grade results cannot be ruled out. Check assays, which are repeat laboratory tests, are pending (ASX announcement, 2 November 2026).
Another Kestrel hole returned 27 metres at 0.57 per cent copper and 0.12 grams of gold per tonne from 120 metres. These are downhole lengths, measured along the hole. The true width, the thickness of the zone at right angles to it, is not yet known. The announcement says drill spacing is not yet enough to show the mineralisation, the metal-bearing rock, is continuous from one line of holes to the next. Chalice is still exploring Kestrel, with follow-up drilling planned after a gravity survey, which measures rock density from the surface (ASX announcement, 2 November 2026).
At the Deep Blue prospect, within Goomalling, Chalice drilled 16 RC holes for 1,874 metres and reported broad low-grade copper, silver and gold zones across 1.2 kilometres of strike. The widest interval listed was 21 metres at 0.18 per cent copper from 50 metres (quarterly report, lodged 27 October 2026). The company reports it as a downhole length and says true widths are not yet known (ASX announcement, 8 September 2026).
Chalice Mining cash and funding
Chalice spent A$6.7 million on exploration and evaluation in the September 2026 quarter, and its cash fell by A$6.7 million. The quarterly cash flow report gives 6.80 quarters of funding, which is the cash divided by the quarter's net operating spending of A$6.6 million. Chalice also held about A$8.2 million of listed investments (quarterly report and Appendix 5B, lodged 27 October 2026).
Every Samso piece on Chalice Mining
3 published pieces as at 17 November 2026, grouped by Samso product. Newest first in each group. Dates are Perth dates.
Samso Research
- 12 Sep 2026, Terra Metals Limited (ASX: TM1) (a workup on Terra Metals that discusses Gonneville as the benchmark for its Southwest discovery)
Samso Insights
- 27 Aug 2026, What a PGE Project Needs Before It Gets Built (an Insight on Southern Palladium's Bengwenyama project that uses Gonneville as its comparison)
- 13 Apr 2025, Chalice Mining Limited: Could A New Flow Chart Reverse Chalice's Falling Fortunes?
Questions people ask about Chalice Mining (ASX CHN)
What does Chalice Mining do? It is studying a palladium, nickel and copper mine at its Gonneville Project, about 70 kilometres north-east of Perth. It also explores for copper and gold.
What is the Chalice Mining share price? The ASX website shows the CHN share price. This page lists Samso's coverage and has no live price.
What is the latest announcement from Chalice Mining? As at 17 November 2026 the newest announcement on the ASX list was lodged on 11 November 2026 and said the Gonneville pilot plant was under way.
Does Chalice Mining have an Ore Reserve at Gonneville? Yes. The Ore Reserve is 260 million tonnes at 0.86 grams per tonne 3E, reported on 8 December 2025.
Is Chalice Mining worth looking at? This page gives no buy, sell or hold call, price target or valuation. Gonneville has an Ore Reserve containing 7.1 million ounces of 3E and a pre-feasibility study. The feasibility study is under way. Funding and the main environmental approvals are still to come. Samso had published no research workup on Chalice Mining at 17 November 2026. The Samso Insight of 13 April 2025 looks at the change to the Gonneville process design.
Disclosure
Samso holds no shares in Chalice Mining at 17 November 2026.
This page is general information only.
Depth over hype.
Samso company research pages are independent research commentary for general information only. Nothing on this page is financial product advice, and it does not take into account any reader's objectives, financial situation or needs. Figures are drawn from public sources believed reliable at the stated dates but are not guaranteed, and market-sensitive numbers change daily. Samso or associated parties may hold positions in, or have commercial arrangements with, companies mentioned. Seek professional advice before making investment decisions. © Samso 2026, samso.com.au